AUTOMATIC TRANSFER SWITCH MECHANICAL VISUAL INSPECTION
Yes
|
No
|
|
1. Inspect for physical damage.
|
||
2. Compare equipment nameplate information and connections with single line diagram and report any discrepancies.
|
||
3. Check switch to insure positive interlock between normal and alternate sources.
|
||
4. Check tightness of all cable connections and bus joints.
|
||
5. Perform manual transfer operation.
|
||
6. Transfer switch and compartment are clean and dust free.
|
||
7. Verify all vendor control cable wiring.
|
||
8. Check terminations and tagging.
|
AUTOMATIC TRANSFER SWITCH ELECTRICAL FIELD TEST
Yes
|
No
|
||
1. Perform insulation resistance tests phase to phase and phase to ground with switch in both alternate and source positions.
|
|||
2. Perform electrical insulation and contact resistance tests as referenced.
|
|||
3. Set and calibrate the Voltage Sensing relays. Contact PDD for settings.
|
|||
4. Set and calibrate the Transfer Time delay relay. Contact PDD for settings.
|
|||
5. Perform automatic transfer by simulating loss of normal power.
|
|||
6. Perform automatic transfer by return to normal power.
|
|||
7. Monitor and verify correct operation and timing of Normal Voltage sensing relays.
|
|||
8. Monitor and verify correct operation and time delay upon transfer.
|
|||
9. Monitor and verify correct operation and timing of Alternate voltage sensing relays.
|
|||
10. Monitor and verify correct operation and timing of Automatic transfer operation.
|
|||
11. Monitor and verify correct operation and timing of mechanical and electrical interlocks and limit switches
|
|||
12. Monitor and verify correct operation and timing, of time-delay and retransfer upon normal power restoration.
|