This fabrication and erection specification of Commissioning High Voltage Circuit Breakers Contactors Switches defines the work practices that are required to properly commission and maintain high voltage circuit breakers/contactors/switches and control. It is not intended to serve as a work scope or limit the extent of work required to operate this equipment.
We will discuss to the visual and mechanical inspections, as well as the electrical and function testing of high voltage circuit breakers/contactors/switches and control.
Commissioning High Voltage Circuit Breakers Contactors Switches
Switches, circuit breakers, and contactors are used to control what parts of an electrical system are energized or de-energized. Fuses are used to protect the electrical system when something goes wrong, and can isolate the faulted parts from the normal parts.
Engineering Documents
- Electrical Equipment Commissioning
- Commissioning: High Voltage Switchgear and/or Contactor Cubicles
- Electrical Work
Commissioning task types
This section defines the responsible personnel types for each of the specific commissioning tasks that appear on the Electrical Commissioning Start-up Checklist. All tasks shall be completed. If a type A or B task is not completed during its appropriate commissioning time, then the A and B task shall be included in the type C commissioning responsibilities.
- “A” – Tasks performed by the contractor, authorized supplier, or electrical technician personnel. Test reports must be provided and available.
- “B” – Pre-energization tasks performed or witnessed by electrical technician personnel. These tasks may be performed by an approved supplier without electrical technical personnel present. Supplier approval shall be given by the appropriate electrical engineering operation support group and Electrical Engineering. Test reports must be provided and available.
- C” – Tasks performed by electrical technician personnel during the commissioning of the equipment.
Electrical commissioning/start-up checklist
High Voltage Circuit Breakers/Contactors/Switches Nameplate Data
Date:___________ Facility:_____________________ Equipment Location:______________________ Project #: _____________
Equipment Designation:______________________________________ Unit # _______ of _______ Units
Manufacturer:_______________________________
Serial number:______________________________
Model number:______________________________ Type:_____________________________________
Equipment Rating:_______________ Volts:_________________ Amps:__________ Amps S/C:___________
Technician:_________________________________________ Sheet # ____ of ____
Visual and Mechanical Inspection for all Equipment
- Upon receipt of the equipment, inspect for physical damage caused by shipping. Report incidences as per shipper’s instructions.
- Compare equipment nameplate information with the latest single line diagram and equipment specifications.
- Ensure proper cell fit and alignment.
- Perform all mechanical operation and contact checks on both the breaker and its operating mechanism in accordance with the manufacturer’s instruction literature.
- Perform normal preventative maintenance using the manufacturer’s instruction literature.
- Verify contact wipe, alignment, spacing, and other parameters which are vital to satisfactory operation. Verify operation of charging mechanism, cutoff switches, and auxiliary relay and/or interlocks. See addition tasks for appropriate special types of equipment.
- Upon completion of above tasks, clean and lubricate the primary and secondary contacts with approved lubricant. Insulation resistance (Megger) test and function test using the remote test stand. Use the test position if the remote test stand is not available.
- Verify the proper and complete operation of all mechanical and electrical interlocks including any key-type system.
Operational and Electrical Testing for all Equipment
- Perform physical wire check and electrically function check each field device to verify that it drops out the proper shutdown relay or starter.
- Calibrate all protective relays in accordance with the latest International Electrical Testing Association (NETA) Acceptance Testing Specification Section 7.9.1 for Electromechanical Relays and 7.9.2 for Microprocessor based relays and applicable manufacturer’s recommendations; Relay software revision and setting file software revision must match. Utilize Electrical Engineering job specific relay settings. Record results. Send as left files to Electrical Engineering.
- Verify that each fail-safe and/or protective relay trips the breaker or starter. Record results.
- Set, check and verify all time delay relays for proper timing and operation.
- Perform contact resistance with the breaker/switch in the closed position using a digital low resistance ohmmeter (Ductor). Refer to the manufacturer’s instruction literature for the maximum value. If there is none listed, use 300 micro-ohms (0003 ohms). Calculate the average of three readings for each phase. The value should be within 10% of each other. Record results:
- Insulation resistance (Megger) test each pole with the breaker/contactor/switch closed. Test phase-to-phase and phase-to-ground for one minute. Record results:
- During the start-up period a jumper log must be maintained. Following control circuit testing check for any “test” jumpers that may have inadvertently been left on.
High Voltage Switch Checks
- Check blade alignment and arc interrupter operation and clearances. Refer to the manufacturer’s instruction literature.
- Check fuse/ linkage and element for proper holder and current rating.
- Exercise switch 2 to 3 times to verify proper operation.
- Ensure line side of switch is terminated on the stationary contact of the switch. Where this is not the case, consult Electrical Engineering.
- Verify spare fuses are the correct rating and the fuse puller is provided.
Vacuum Circuit Breaker/Contactor Checks
- Perform a high potential test on each interrupter for one (1) minute.
- Caution: Read manufacturer’s instruction literature concerning the X-radiation hazards and voltage levels. Record results.
- Verify tolerances for erosion, contact travel, and overtravel as per manufacturer’s instruction literature.
- Verify initial contact wear position indicator.
- Refer to the manufacturer’s instruction literature under the installation and maintenance sections to describe procedures and checks recommended.
SF6 Circuit Breakers Checks
- Refer to the manufacturer’s instruction literature under the installation and maintenance sections to describe procedures and checks recommended.
- Verify SF6 low pressure alarm in accordance with manufacturer’s published data.
Documentation
Complete nameplate data information and test results.
Complete Report 1, Electrical Protective Device Verification Report.
Complete Report 2, Circuit Breaker/Contactor/ Switch Test and Inspection Report.
One copy of the completed documentation shall be filed on site for future reference and one copy shall forwarded to Air Products PDO Electrical Engineering.
Report 1
Electrical Protective Device Verification Report | Date:__________ |
Facility:__________________ Equipment Location: __________________ Project :______________
Equipment Designation/Tag #:__________________________ Unit # ________ of ____________ Units
Manufacturer:_____________________________ Serial number:______________________________
Model number:____________________________ Type:______________________________
Equipment Rating:____________________ Volts:_________________ Amps:___________________
Technician:___________________________ Test Set:________________ Sheet # ______ of ______
Device Function | Function | Trip Function | Phase | Tested | |||
Number | 86 L0. | Breaker | By Date | ||||
50 | Instantaneous
Overcurrent (IIT) |
||||||
51 | Time Overcurrent
(ITH&CO) |
||||||
74 | Time Overcurrent
Alarm (CO) |
||||||
47 | Undervoltage Phase Sequence | ||||||
87 | Current Differential | ||||||
40/48 | DC Field Failure/
Incomplete Sequence |
||||||
55/48 | Power Factor/
Incomplete Sequence |
||||||
46 | Phase Balance
Current Relay |
||||||
27 | Breaker D.C.
Undervoltage Release (Emergency Trip) |
||||||
27 | DC Control Circuit
Undervoltage |
||||||
81 | Underfrequency | ||||||
26 | D.C. Field Thermal Trip | ||||||
49 | Stator Temperature | ||||||
62-1 | Auxiliary Device Time
Delay Trip |
||||||
62-2 | Auxiliary Device Time
Delay Trip |
||||||
50 GS | Instantaneous Ground
Current (ITH) |
Remarks:__________________________________________________________________
_________________________________________________________________________________
Report 2
Circuit Breaker/Contactor/Switch
Test and Inspection Report |
Date:__________ |
Facility:__________________ Equipment Location: __________________ Project #:______________
Equipment Designation/Tag #:__________________________ Unit # ________ of ____________ Units
Manufacturer:_____________________________ Serial number:______________________________
Model number:____________________________ Type:______________________________
Equipment Rating:_____________ Volts:_____________ Amps:___________ Amps S/C: _____________
Technician:___________________________ Test Set:________________ Sheet # ______ of ______
OUTAGE TYPE | EQUIPMENT FUNCTION | Equipment Designation | ||||||||
Scheduled | Distribution Feeder/Breaker/Switch | |||||||||
Unscheduled | Motor Feeder Breaker/Contractor | Manufacturer | ||||||||
Starting Breaker/Contactor | ||||||||||
Running Breaker/Contactor | Voltage | |||||||||
Neutral Breaker/Contactor | ||||||||||
PROTECTIVE RELAY INSPECTION | I.B. | |||||||||
Calibrated | Other: | |||||||||
Function Tested | Drive Motor Type | |||||||||
Visual Inspection Only | N/A | Induction Synchronous N/A | ||||||||
FAIL-SAFE CIRCUIT CHECKLIST | ||||||||||
Device Number | Specification | As Found | As Left | |||||||
Circuit Revisions or Changes | ||||||||||
Switchgear Counter Reading | Start | Finish | ||||||||
Switchgear Unit Number | ||||||||||
Switchgear
Checklist |
Inspected Adjusted_____________________________________________ Cleaned
Tested Meggered ( to and to GND) Contact Condition Lubricated Tightened Connections ____________________ Repaired |
|||||||||
Remarks | Field Excitation Equipment |
Stand Alone Rectifier – E.P.M. Complete Yes No
Field Application Panel – E.P.M. Complete Yes No |
||||||||