1. What is Standard in Aramco related to Building works;
a) SAES A
b) SAES P
c) SAES Q
d) SAES M
2. If the quantity of concrete for building wall is 115.4 cubic meters how many concrete cylinder samples to be casted;
a) 4
b) 5
c) 6
d) 8
3. The minimum pavement thickness for concrete is what;
a) 100 mm
b) 150 mm
c) 200 mm
d) None of the above
4. The compressive strength for pre-cast concrete is ;
a) 3000 psi
b) 2000 psi
c) 4000 psi
d) None of the above
5. The revolution of concrete mixer shall not more than;
a) 2 rpm
b) 3 rpm
c) 4 rpm
d) None of the above
6. The concrete vibrator shall be placed in concrete mix at space distance of minimum of;
a) .30 m
b).40 m
c).60 m
d) None of the above
7. ASTM means;
a) American Society for Material and Testing
b) American Society for Testing Materials
c) American Standards for Material and Testing
d) None of the above
8. When to start curing work for concrete;
a) After 2 hours upon finishing
b) After 3 hours upon finishing
c) After 4 hours upon finishing
d) None of the above
9. What are column stirrups differs to column ties;
a) Bigger the stirrups to ties
b) Smaller the stirrups to ties
c) Spacing requirements
d) None of the above
10. Honey combed is caused by;
a) Poor vibration of concrete
b) Too much water of concrete
c) Poor placing of concrete
d) None of the above
11. The contraction joint of building pavement is;
a) 3m
b) 4m
c) 5m
d) None of the above
12. Make a sample of Internal NCR for Building Works (5 points)
13. How to initiate RFI? Please indicate the step by step procedure. ( 5 points)
14. Give at least 5 important duties and responsibilities of Concrete Building Inspector. (5 points)
15. How to control concrete placement for walls /columns and other building structures? (5 points)