Switch Valves Commissioning Checklist:

  • Valve nameplate verified per specification sheet.
  • Valve in correct physical location.
  • Correct flow direction.
  • Lubricator/filter piping installed to drawing.
  • Operator correctly orientated.
  • Accessible for maintenance.
  • Accessible for removal.
  • Air supply provided. Set at correct pressure. Blown down.
  • Actuator fail position correct.

Solenoid Valves and Limit Switches Commissioning Checklist

  • Correct orientation.
  • Wiring checked:
    • – Correct
    • – Continuity
    • – Insulation
  • Connection to solenoid coil strain relieved.
  • Explosion-proof requirement checked.
  • Limit switch coupling/cam set-screws tight.
  • Limit switch cams lubricated.