POWER TRANSFORMER TESTING ON SITE (SITE ACCEPTANCE TEST SAT)

current transformer

Main tests are Transformer testing, transformer oil testing, transformer winding, current transformer, Transformer Ratio test.

TRANSFORMER TESTING ON SITE

After a transformer has been completely assembled on site, it must be tested to confirm successful shipment and correct assembly. All tests must be carried out with instruments that have traceable, valid calibration. These instructions are intended to provide guidelines in the test of transformers to maintain their quality and reliability.

They are intended for the guidance of personnel who have been trained for, or who have experience in test of high-voltage electrical power equipment, including the use of good safety practices. These instructions are intended to supplement, and not eliminate the necessity for such training.

The Transformer testing results are to be recorded on a Test Record. The second sheet of this Transformer testing Record is a list of all possible tests, some of which may not be applicable. When the on-site project manager or the assembly supervision has marked all applicable tests, this sheet forms an order-bound directive for the tests to be carried out.

Main tests are Transformer testing, transformer oil testing, transformer winding, current transformer,Transformer Ratio test.

Transformer Ratio test

The Transformer Ratio test is used to confirm that the winding turns ratio is consistent with the voltage ratio as shown on the Nameplate.

Transformer Ratio test
This is done primarily to check for shipping damage and to confirm that any tap-changer leads installed in the field have been correctly connected. In addition to the ratio measurement, exciting current is also often measured. The ratio measurements is normally done with a ratio bridge. Table of three-phase transformer connections Appendix 1. Transformer Ratio test

transformer ratio test
Transformer testing
transformer oil testing
transformer winding
transformer turn ratio

Transformer Winding resistance test

Measure the resistance of each winding at the rated and extreme tap positions and compare the results to the original value in the Factory test report. If the Tap Changer connections have been made at site, measuring at all positions should be done. Transformer winding Resistance is dependent on the temperature of the winding. The mean temperature of the oil is representative of the winding temperature, and providing that the oil is at a uniform temperature, the top oil temperature gauge value can be used. Resistance comparison must always be made at a common temperature. The conversion formula for copper and aluminium transformer winding is show below. The formula giving the relation between the resistance and the temperature is:

winding resistance test

where RT2 = Resistance of the winding at temperature T2
RT1 = Resistance of the winding at temperature T1
K = 234.5 for winding made of copper ace to IEEE,
K = 235 for winding made of copper ace IEC
K = 225.0 for winding made of aluminium
The time constant may be very long when low voltage and low current sources are used.

Note: 

A high voltage surge occurs at interruption of DC current at end of measurements. A discharge circuit should be used. Eg. see IEEE Std 62 figure 2.

Main tests are Transformer testing, transformer oil testing, transformer winding, current transformer, Transformer Ratio test.

Transformer Check of vector group

The purpose of this series of tests is to check the polarity and the phase relationship of the multiple windings in a transformer. The test is carried out simultaneously with the transformer turns ratio test when using a turns ratio test set. In order to define the connection of a three-phase transformer and to facilitate the parallel connection with other transformers, the international standards prescribe specific vector groups. Every country has its own designation for the vector groups. IEC and IEEE (in USA) have recommended a method that will result in standardized and fully defined designations.

Transformer Insulation resistance test

Insulation resistance can give some information of the integrity of the insulation structure. As an insulation structure begins to deteriorate due to contamination and moisture, the insulation resistance will decrease. The test equipment used is a DC insulation tester (Megger). It is essential that it is of a type, which is suitable for measurement on transformers and transformer core insulation. Ensure that bushings are clean and dry. Insulation resistance is temperature dependence why it is important that the oil temperature is noted.
After the test has been completed, all terminals shall be grounded time enough to allow any trapped charge to decay to negligible value.

Transformer main windings

When conducting an insulation resistance test on transformer windings, a 2.5 or a 5 kV megger can be used. Test every winding to ground and between each winding. Make sure that the bushing porcelains are cleaned since dirt deteriorates the insulation resistance. The transformer tank must be grounded during the test. If the insulation resistance is 1 Mn/kV system voltage for the winding, it is acceptable. If lower values are measured, this must be reported to an ABB representative.
According to IEEE the following shall be measured. High voltage to low voltage and ground, low voltage to high voltage and ground.

Read more

POWER CABLE INSTALLATION AND TERMINATION

POWER CABLE INSTALLATION AND TERMINATION

POWER CABLE INSTALLATION AND TERMINATION

REFERENCES AND INTERNATIONAL STANDARDS FOR POWER CABLE INSTALLATION

M7.12.12      Wire and Cable Specification

IEC 60050    International Electro-Technical Vocabulary

IEC 60055    Paper Insulated Metal Sheath Cables For Rated 1KV to 30KV

IEC 60173    Colours of the Cores of Flexible Cables and Cords

IEC 60183    Guide to the Selection of HV Cables

IEC 60228    Conductor of Insulated Cables

IEC 60287    Calculation of the Continuous Current Rating of Cables

IEC 60331    Fire Resisting Characteristics of Electrical Cables

IEC 60332    Tests on Electrical Cables under Fire Conditions

IEC 60364    Electrical Installation in Buildings

IEC 60446    Colour Identification-Insulated & Non-Insulated Core

IEC 60502    Extruded Sold Dielectric Insulated Power Cables for Voltages from 1KV to 30KV

IEC 60540    Test Methods for the Insulation & Sheaths of Electrical Cables & Cord (Elastometric & Thermoplastic Compounds)

IEC 60754    Tests on Gas Evolved During Combustion of Electric Cables

IEC 60811    Common Tests Methods for Insulating & Sheathing Materials of Electric Cables

IEC 60851    Methods of Test for Winding Wires

IEC 61034    Measurement of Smoke Density of Electric Cables Burning Under Defined Conditions, Test Procedures & Requirement

IEC 61158-2   H1 Field bus cables

PROCEDURE POWER CABLE INSTALLATION

    • Cable installation shall comply with reference codes and design documents.
    • All cable drum shall be checked with packing list and confirmed no mechanical damage.
    • During cable drum shifting; check mechanical damage, nameplate with cable schedule & drum list and phase rotation of the cable.
    • Assure necessary PPE, tools and equipment for cable pulling. Check the latest cable drum list and cable schedule. Prior for cable pulling, QA/QC inspector shall check if all the cable supports are installed and fixed.
    • All wire and cable shall be megohm meter tested after it is pulled, but prior to termination.
    • High voltage cable shall be given a hi-pot test after it is pulled and stress relief is installed, but prior to termination.
    • Electrical cables shall be oil & sunlight resistance and flame retardant shall be used as per IEC 60332.
    • Cables used for buried or external installation shall be steel wired armoured. Noted that armouring cables are not required within the building, e.g. from control room to control building rack room
    • Cables shall be installed direct buried on the ground or in formed concrete trenches with backfill, fastened to cable ladder rack or tray and in underground ducts.
    • Make check for the following during wire and cable installation;
      1. The proper type, size, colour and number of wires & cables are being installed.
      2. For long pulls, the pull is performed as per required pulling tension.
      3. Cable is not pulled around too many bends.
      4. Ambient temperature is above the minimum allowed for the cable insulation.
      5. Proper pulling compound is being used.
      6. For long pulls, allowable pulling tensions are not exceeded.
      7. Cables are not bent on too tight a radius.
      8. Wire and cable is protected and kept clean throughout the pulling operation.
      9. Cable fill does not exceed NEC requirements.

 

Read more

Electrical Heat Tracing Testing Procedure

HEAT TRACING INSTALLATION AND TESTING

Electrical Heat Tracing Testing Procedure

  1. QC inspection for completed heating cables devices and steel supports shall be requested and inspection/test result shall be filed and recorded on appropriate inspection forms.
  2. Visual inspection shall include dimensional check for junction box, support inspection and location verification to be recorded in approved inspection forms.
  3. Conduct preliminary testing prior to final inspection ensuring all connections and function are appropriate with respect to wiring diagram and other requirements
  4. Verify set points match caution signs.
  5. With circuit energized for 5 minutes measure current and voltage of each phase. Compare measure value to design value at the current cable temperature and note discrepancies. Deviations in excess of + or – 10% shall be investigated. Follow the site electrical repetitive procedures for voltage checks.
  6. Adjust thermostat/temperature set point to final settings in accordance with engineering drawings and specifications.
  7. Inspect the cladding for damage and water seal.
  8. Inspect for environmental conditions, e.g. abnormal ambient temperature, mildew, moisture, condensation, dust and dirt.
  9. Before thermal insulation is installed the continuity and insulation resistance test to be carried out on heating cable by applying 500 VDC or 2500 VDC depending upon the types of cable. The minimum acceptable IR value is 20 mega ohms.
  10. RTD Resistance Test to be done.
  11. After the thermal insulation is installed the continuity and resistance test to be repeated again on heating cable by applying 500 VDC or 2500 VDC depending upon the types of cable. The minimum acceptable IR value is 20 mega ohms.
  12. For normal LV cables continuity and insulation resistance test to be carried out.

 

Read more

HEAT TRACING INSTALLATION AND TESTING

HEAT TRACING INSTALLATION AND TESTING

HEAT TRACING INSTALLATION AND TESTING

Preparatory Works for Heat Trace Installation

  1. Ensure that work permit is prepared and secured. Safety concern and precautions are being complied and discuss with the crew.
  2. Subcontractor shall appoint qualified employees as their ‘competent persons’. Such persons shall be capable of working safely and shall be knowledgeable on the precautionary techniques, personnel protective equipment for the installation of heat tracing.
  3. Equipment, tools and other logistics shall be prepared and are ready for installation of heat tracing.
  4. Material Handling prior to installation of heat tracing.
  5. Identify the heating cable to ensure proper type and quantity is received.
  6. Cable model number shall be visible on the parallel heating cables (on braided cables, information is printed on the jacket below the braid).
  7. Visually Inspected material for damage incurred during shipment.

Work flow documents for heat tracing hand-over

  • Piping QC will handover released package to Electrical Team.
  • Mechanical QC will handover released package to Electrical Team.
  • After completion of electrical work Electrical QC will handover released package to Insulation.
  • After completion of electrical work Electrical QC will handover released package to Insulation.
  • Document handover with duly accomplished Work Transfer

Preparatory Works for Heat Trace Testing

  1. Review appropriate supplier literature, design drawings and specifications before starting the job.
  2. Compare heater cable, connection and end seal kits and all associated tracing components manufacturers and model number against drawing and specification.
  3. Visually inspect heater cable for damage, correct installation at pipe shoes and other heat sinks.
  4. Correct installation tape spacing, heater orientation on pipe and overall general construction installation.
  5. Check the design heater length against the actual length (start and stop cable lengths may be printed on the heater).
  6. Inspect end seals for proper sealing and installation.
  7. Inspect connection kit for proper location sealing and installation.
  8. Inspect RTD for correct type, securely taped to pipe at the right location, damage (such as field bending) and correct wiring.
  9. Verify continuity of heater cable. This to be documented at receipt of material on reel, after the heater cable is installed and after insulation is installed.
  10. Measure insulation resistance of each heater cable conductor. This is to be documented at receipt of material on reel, after the heater cable is installed and after insulation is installed.

 

Read more

error: Content is Protected.