CCR Reactor Site Assembly Installation Procedure

CCR Reactor Site Assembly Installation Procedure

Contents

► CCR Reactor General Information
►CCR Reactor Internal Parts
►CCR Reactor Layout

CCR Reactor General Information

CCR Reactor General Information

CCR Reactor General Information

CCR Reactor General Information

CCR Reactor Shipping Condition

CCR Reactor Site Assembly Installation Procedure

CCR Reactor Internal Parts

Access way only form Top Manhole (1.D. 2000 mm )

► Plumbness and clearance requirement for catalyst tight
► Confined space in the Reactor
► Smooth flush on welding bead of catalyst contact face
► Layout in the CCR unit structure

CCR Reactor Internal Parts

CCR Reactor Internal Parts Information

Feed Diffuser Outer grid

  1. Center Pipe.
  2. Sealing ring (3pcs/segment type).
  3. Conical cover (6pcs/segment type).
  4. Cover Plate(12pcs/segment type).
  5. Catalyst transfer pipe(12pcs/Rx) with sealing ring.

Installation by Rx vendor at shop.
CCR Reactor Internal Parts Information

CCR Reactor Internal Scope of Inspection

Parts

Trial assembly

Location for trial assembly

Final Installation

Outside Grid Same allocation in
the reactor
Internal vendor shop Reactor vendor
Center pipe Conical cover and cover plate shall be installed to center pipe in vertical position Site
Conical cover same as above Site
Cover plate same as above Site
Catalyst inlet pipe Seal Ring Associated stopper Inspection alone Flange neck to be welded at site. Internal vendor shop Site
Sealing ring Fitting with center pipe Internal vendor shop  Site

CCR Reactor Internal Outside Grid

CCR Reactor Internal Outside Grid

CCR Reactor Internal Outside Grid

CCR Reactor Internal Outside Grid

CCR Reactor Internal Outside Grid

CCR Reactor Internal Outside Grid

CCR Reactor Internal Outside Grid

Outside Grid Top Section

Four( 4 )-Guide Plate shall be adjusted to make nominal clearance 10mm.  Temporary stiffeners and support jigs for shipping shall be removed at site.

Outside Grid Top Section

CCR Reactor Internal Parts Outside Grid Support Ring

Temporary bolts will be installed at Reactor vendor shop. Bolt and Spacer shall be replaced for operation at site.

CCR Reactor Internal Parts Outside Grid Support Ring 

6. Complete Grid Support Ring Machining at Bottom Head

CCR Reactor Internal Parts Outside Grid Support Ring 

Plumbness for outside Grid.

This plumbness shall be inspected after erection of reactors at site.

CCR Reactor Internal Parts Outside Grid Support Ring 

Temporary shipping lugs for outside grid shall be removed after erection of reactor.

CCR Reactor Internal Parts Outside Grid Support Ring 

CCR Reactor Internal Parts Outside Grid Support Ring 

CCR Reactor Internal Centre Pipe & Sealing Rings

No.4 Reactor

Dia. 1.9m x L2om, weight 10 ton.
Center pipe to be installed at site

CCR Reactor Internal Centre Pipe & Sealing Rings

(Temporary) Lifting lugs and tailing lugs shall be supplied by internal vendor. Recommended loading procedure for center pipe shall be submitted by internal vendor.

CCR Reactor Internal Centre Pipe & Sealing Rings

CCR Reactor Internal Centre Pipe & Sealing Rings

CCR Reactor Internal Centre Pipe & Sealing Rings

CCR Reactor Internal Parts Center Pipe

CCR Reactor Internal Parts Center Pipe

Annular spacing between center pipe and outside grid.

CCR Reactor Internal Parts Center Pipe

CCR Reactor Internal Parts Sealing Ring

CCR Reactor Internal Parts Sealing Ring

CCR Reactor Internal Parts Sealing Ring

Lowering these rings before lowing center pipe.
Loading weight for these parts to be confirmed.

CCR Reactor Internal Parts Sealing Ring

CCR Reactor Internal Parts Sealing Ring Rx No. 1

CCR Reactor Internal Parts Sealing Ring Rx No. 1

CCR Reactor Internal Conical Cover & Cover Plate

CCR Reactor Internal Conical Cover & Cover Plate

CCR Reactor Internal Parts – 5-Conical Cover Guide Plate

CCR Reactor Internal Parts

CCR Reactor Internal Parts – 1-Center pipe positioning plate

CCR Reactor Internal Parts

CCR Rx Internal Parts – Catalyst inlet pipe ( 12 pcs/Rx)

CCR Rx Internal Parts - Catalyst inlet pipe

5.2. PIPE TO PIPE OR PIPE TO VESSEL EY FLANGE (FOR PNEUMATIC AND GRAVITY FLOW)

Requirement for Catalyst line pipe

Requirement for Catalyst line pipe

CCR Reactor Internal Parts – Sealing Ring & Associated Stopper

CCR Reactor Internal Parts - Sealing Ring & Associated Stopper

CCR Reactor Internal Parts - Sealing Ring & Associated Stopper

CCR Rx Internal Parts – Pressure Connection

CCR Rx Internal Parts - Pressure Connection

CCR Reactor Layout

Applicable items for R-2151-101 14 ITEMS

> NO.1-4 REACTORS
> REGENERATOR
> REDUCTION CHAMBER
> NO.2-4 UPPER HOPPER
> NO.1-5 LOWER HOPPER

CCR Reactor Layout

Plot Plan NHR/SPRITTER/CCR/ISOME

Plot Plan NHR/SPRITTER/CCR/ISOME

Plot Plan NHR/SPRITTER/CCR/ISOME

CCR Reactor & Hopper

CCR Reactor & Hopper

CCR Reactor & Hopper

CCR Unit Piping Connection Design

Butt Weld Joint for Piping

CCR Unit Piping Connection Design

Reactor & Hopper Construction

Reactor & Hopper Construction

Reactor & Hopper Construction

 

 

Leave a Comment

error: Content is Protected.