Electrical Project Deliverables | Electrical Deliverables List

This article is about Electrical Project Deliverables related to topic of Electrical Deliverables List as per International Codes & Standards. Here furthermore will be discussed about Electrical and Instrumentation Project Deliverables Examples, Detailed Electrical Engineering Deliverables List,  Project Deliverables Matrix, Electrical Engineering Deliverables Sequence, Electrical Deliverables List, Electrical Design Deliverables List,
Deliverables of Construction Project in Plant and Petrochemical Plants.

Electrical and Instrumentation Project Deliverables Examples, Detailed Electrical Engineering Deliverables List,  Project Deliverables Matrix, Electrical Engineering Deliverables Sequence, Electrical Deliverables List, Electrical Design Deliverables List, Deliverables of Construction Project in Plant and Petrochemical Plants.

Electrical Project Deliverables | Electrical Deliverables List

Following are the list of Electrical Project Deliverables list and Document numbers shall be assigned in numerical order following sequence.

    1. Drawing Index Create using Standard Deliverable TEMPLATE ELEC 0040 from the document storage system. This will be a living document for the duration of the detailed design phase.
    2. General Notes – Create using Standard Deliverable TEMPLATE ELEC 0007 SH.01 from the document storage system.
    3. Medium Voltage Single Line Diagram – Create using Standard Deliverable STD-DELIV ELEC 0040 from the document storage system. Voltage level of the single line shall appear in both the placeholder and drawing title. Drawing content requires the finalized Medium Voltage Single Line obtained from electrical engineering and vendor drawings for the medium voltage equipment. Reference 3EL61001 for single line drawing content.
    4. Low Voltage Single Line Diagram – Create using Standard Deliverable STD-DELIV ELEC 0040 from the document storage system. Voltage level of the single line shall appear in both the placeholder and drawing title. Drawing content requires the finalized Low Voltage Single Line obtained from electrical engineering and vendor drawings for the Low voltage equipment. Reference 3EL61001 for single line drawing content.
    5. Medium Voltage (>1000 volts) Control Schematic – Create using Standard Deliverable STD-DELIV ELEC 0051 from the document storage system. Drawing content requires the P&ID, I/O list, load list, medium voltage single lines, and vendor drawings for the medium voltage equipment.
    6. Low Voltage AC Equipment (>240 volts and <1001 volts) Control Schematics – Create using Standard Deliverable STD-DELIV ELEC 0051 from the document storage system. Drawing content requires the P&ID, I/O list, load list, low voltage single lines, and vendor drawings for the low voltage equipment.
    7. Low Voltage AC Equipment (<241 volts) Control Schematics – Create using Standard Deliverable STD-DELIV ELEC 0051 from the document storage system. Drawing content requires the P&ID, I/O list, load list, low voltage single lines, and vendor drawings for the low voltage equipment.
    8. Low Voltage 24 VDC Control Schematics – Create using Standard Deliverable STD-DELIV ELEC 0051 from the document storage system. Drawing content requires the P&ID, I/O list, load list, and vendor drawings for the 24 VDC equipment.
    9. Low Voltage Panel board Schedules – Create using Standard Deliverable STD-DELIV ELEC 0005 SH.01 from the document storage system. Drawing content requires the I/O list, load list, vendor drawings for the electrical equipment, and information generated during the design effort.
    10. Underground Grounding Grid document – Create using Standard Deliverable STD-DELIV ELEC 0013 SH.01 from the document storage system. Drawing content requires the equipment arrangement drawing, general arrangement drawing, piperack layout drawings, vendor equipment drawings, and information generated during the design effort. The Underground Grounding Grid document(s) shall be broken down by area with sheet 1 showing the entire plant or area and indicating which drawing sheet details each area.
    11. Underground Conduit document – Create using Standard Deliverable STD-DELIV ELEC 0013 SH.01 from the document storage system. Drawing content requires the equipment arrangement drawing, general arrangement drawing, piperack layout drawings, vendor equipment drawings, and information generated during the design effort. The Underground Conduit document(s) shall be broken down by area with sheet 1 showing the entire plant or area and indicating which drawing sheet details each area.
    12. Cable tray Layout documents – Create using Standard Deliverable STD-DELIV ELEC 0033 from the document storage system. Drawing content requires the appropriate standards and standard drawings obtained from the document storage system and information from the General Arrangement drawings, Piperack drawings, and Structural Support drawings. The Cable tray Layout document(s) shall be broken down by area with sheet 1 showing the entire plant or area and indicating which drawing sheet details each area. Each cable tray, wire way, conduit, or other raceway shown on the design drawings shall have a unique identifying number such as CT1 for cable tray 1. The raceway identifiers shall appear on all documents where they are referenced.
    13. Lighting and Utility Plan document(s) – Create using Standard Deliverable STD-DELIV ELEC 0011 from the document storage system. Drawing content requires the appropriate standards and standard drawings obtained from the document storage system and information from the General Arrangement drawings and Equipment Layout drawings. The Lighting and Utility Plan documents shall be broken down by area with sheet 1 showing the entire plant or area and indicating which drawing sheet details each area. If a higher degree of detail is required to meet project requirements the Electrical Designer may choose to use Standard Deliverable STD-DELIV ELEC 0037 “Lighting Plan (Plant, Process Area, Description)” and Standard Deliverable STD-DELIV ELEC 0038 “Utility Plan”. Separate document numbers are required for each Standard Deliverable type used with sheet 1 of each type showing the entire plant or area and indicating which drawing sheet details each area.
    14. Heat Trace Schedule document – Create using Standard Deliverable TEMPLATE ELEC 0043 from the document storage system. Drawing content requires the appropriate standards and standard drawings obtained from the document storage system and information from the Project P&IDs, Piping Isometrics, Vendor equipment documents and Equipment Layout drawings. Electrical design shall be responsible for specification and creation of freeze protection heat trace documentation. Electrical design shall not be responsible for the specification or control methodology of process maintenance heat trace. Heat trace used to maintain temperatures for process lines, vessels, and equipment shall be specified by the Process Engineering group or designee and Process Systems or designee shall be responsible for proposing the maintenance heat trace control methodology. Electrical design shall be responsible for creating the electrical schematics and documentation to power and control the maintenance heat trace. When the design indicates that Heat Trace terminal enclosures are required, the Electrical Designer shall incorporate the Heat Trace Junction Box Fabrication drawings as a separate sheet number under the Heat Trace Schedule document number.
    15. Terminal Box Tabulation documents – Create using Standard Deliverable STD-DELIV ELEC 0014 SH.01 from the document storage system. Drawing content requires the I/O list, load list, vendor equipment data, Project P&IDs, General Arrangement drawings and Equipment Layout drawings.
    16. Control/Junction Box Fabrication documents – Create using Standard Deliverable STD-DELIV ELEC 0044 from the document storage system. Drawing content requires the I/O list, load list, vendor equipment data, Project P&IDs and information generated during the design effort. Control/Junction Box Fabrication drawings include, but are not limited to AC Control/Junction Boxes, DC Control/Junction Boxes, Smoke Alarm panels, System Alarm panels, System Monitoring panels, Interposing Relay panels, ICP Shutdown Panels, Medium Voltage Remote Control Panel, etc..
    17. AC Interconnect Wiring Diagram document(s) – Create using Standard Deliverable STD-DELIV ELEC 0019 SH.01 from the document storage system. Drawing content requires the I/O list, load list, vendor supplied Electrical Equipment data, Project P&IDs and information generated during the design effort. The AC Interconnect Wiring Diagram document shall be broken down by area with each area given a unique document number. Multiple AC Interconnect Wiring Diagram drawings for a given area shall be given a single document number with individual sheets detailing each Interconnection drawing.
    18. DC Interconnect Wiring Diagram documents – Create using Standard Deliverable STD-DELIV ELEC 0019 SH.01 from the document storage system. Drawing content requires the I/O list, load list, vendor supplied Electrical Equipment data, Project P&IDs and information generated during the design effort. The DC Interconnect Wiring Diagram document(s) shall be broken down by area with each area given a unique document number. Multiple DC Interconnect Wiring Diagram drawings for a given area shall be given a single document number with individual sheets detailing each Interconnection drawing.
    19. AC Power and Control Cable Schedule documents – Create using Standard Deliverable TEMPLATE ELEC 0041 from the document storage system. Drawing content requires the I/O list, load list, single line, vendor equipment data, Project P&IDs and information generated during the design effort. The AC Power and Control Cable Schedule documents shall be broken down by area with sheet 1 showing the entire plant or area and indicating which sheet details each area. Multiple AC Power and Control Cable Schedule documents for a given area shall be given a single document number with individual sheets detailing each AC Power and Control Cable Schedule document.
    20. DC Power and Control Cable Schedule documents – Create using Standard Deliverable TEMPLATE ELEC 0042 from the document storage system. Drawing content requires the I/O list, load list, single line, vendor equipment data, Project P&IDs and information generated during the design effort. The DC Power and Control Cable Schedule documents shall be broken down by area with sheet 1 showing the entire plant or area and indicating which sheet details each area. Multiple AC Power and Control Cable Schedule documents for a given area shall be given a single document number with individual sheets detailing each DC Power and Control Cable Schedule document.
    21. Building Plan Detail documents – Create using Standard Deliverable STD-DELIV ELEC 0009 SH.01 from the document storage system. Drawing content requires the vendor supplied data, project requirements, and Plant Design information obtained from the document storage system and applicable disciplines, and information created during the design. The Building Plan Detail documents shall be broken down by building type or purpose. Each building type will have a unique document number with individual sheets detailing building layouts details. Electrical Buildings, Analyzer Buildings, Control Buildings, Maintenance Buildings, Compressor Buildings, Pump Houses, Waste Water Treatment Buildings, Garages, and Miscellaneous Buildings                                                               
      • Sheet 1 – General Arrangement (GA) including outdoor equipment such as transformers and capacitor banks. The GA shall show equipment locations and dimensions, to scale, to show the locations of equipment installed inside the building.
      • Sheet 2 – Power and lighting wiring details.
      • Sheet 3 – Cable Tray/Raceway Layout details.
      • Sheet 4 – Building penetrations including wall penetrations for cable tray, arc blast duct, bulkheads, etc and floor penetrations for underground conduit or duct.
      • Sheet 5 – Equipment section views and details.
      • Sheet 6 – Fire Alarm/Atmospheric Monitoring System plans and details.
      • Sheet 7 on – Miscellaneous Details, Bills of Material, Cable or Bus Duct Details, etc. When more than one sheet is required to show all details or multiple levels the sheet number shall be suffixed with A, B, C, etc.
    22. Plant Plan and Details documents – Create using Standard Deliverable STD-DELIV ELEC 0009 SH.01 from the document storage system. Drawing content requires the vendor supplied data, project requirements, and Plant Design information obtained from the document storage system and applicable disciplines, and information created during the design effort. Plant Plan and Details drawings include, but are not limited to location drawings for ground pigtails, field mounted e-stops, lube oil heaters, vacuum blowers, pump motors, field mounted disconnect switches, motor heater terminal boxes, motor terminal boxes, motor CT terminal boxes, motor instrument terminal boxes, vendor supplied junction boxes, APCI supplied junction and terminal boxes, field mounted analyzer and I/O panels, remote PES panels, and control panels.
    23. Plant Bill of Material documents – Create using Standard Deliverable TEMPLATE ELEC 0044 from the document storage system. Drawing content requires the information created during the design effort.
    24. Electrical Equipment Connection documents – Create using Standard Deliverable STD-DELIV ELEC 0044 from the document storage system. This document is used when cable to equipment connections are not in separate enclosures or when cables can come in contact with energized components; for example, dry type medium voltage motor starting reactors. Document shall detail required cable separation clearances, cable mounting and support details and cable connection details. Drawing content requires information from the electrical engineer and the vendor installation drawings and manuals.  Note:  Special attention to drawing detail is required when the electrical designer designs for a “one-off” application. The electrical designer shall meet with the appropriate discipline to discuss any special requirements for the equipment and to review the vendor’s information.
    25. Hazardous Area Classification Drawing documents – Create using Standard Deliverable STD-DELIV ELEC 0006 SH.01 from the document storage system. Drawing content requires the Plot Plan and information from the Project Manager, Project Development Engineer, and Environmental, Health and Safety Department.
    26. Fiber Optic Cable Details documents – Create using Standard Deliverable STD-DELIV ELEC 0009 SH.01 from the document storage system. Drawing content requires information from the Electrical Engineer, Process Controls Engineer, Security, and Information Technology (IT) to determine the type of communication equipment, their locations, cable type, and cable routing that will be utilized on the project.
    27. Medium Voltage Motor/Transformer Phasing documents – Create using Standard Deliverable STD-DELIV ELEC 0040 from the document storage system. Drawing content requires Electrical Standard 28-4EL64476A “Motor Phasing Form”, the information from the Single Line Diagram, Motor Vendor Data, and Electrical Engineering.
    28. High Voltage Cable Design Form documents – Create using Standard Deliverable TEMPLATE P710 0001 from the document storage system. To make high voltage cable design form Document requires information from the Single Line Diagram, AC Power and Control Cable Schedule and Electrical Engineer.
    29. High Voltage Cable Order Form document(s) – Create using Standard Deliverable TEMPLATE P710 0002 from the document storage system. To make high voltage cable order form Document requires information from the High Voltage Cable Design Form, Single Line Diagram, AC Power and Control Cable Schedule and Electrical.
    30. High Voltage Cable, Project Transmittal Requisition documents – Create using Standard Deliverable TEMPLATE P710 0003 from the document storage system. Document content requires information from the High Voltage Cable Order.
    31. Terminal Lug Order Form documents – Create using Standard Deliverable TEMPLATE P750 0001 from the document storage system. Document content requires information from the High Voltage Cable Design Form.
    32. Termination Kit Order Form document(s) – Create using Standard Deliverable TEMPLATE P750 0002 from the document storage system. Document content requires information from the High Voltage Cable Design Form.
    33. Project Transmittal Requisition – Terminal Lugs and Termination Kits document(s) – Create using Standard Deliverable TEMPLATE P750 0003 from the document storage system. Document content requires information from the Terminal Lug Order Form and the Termination Kit Order Form.

Refer to ( ELECTRICAL DESIGN WORK PROCEDURE ) for document approval matrix.

Hazardous Area Requirements for Class I Areas – Electrical Installation