Excavation, Placement and Compaction Technical Requirements

Excavation, Placement and Compaction Technical Requirements in Subkha Areas

“Minimum trench width from the bottom to 300 mm above the top of the pipe shall be as follows:

Type of Pipe             Nom. Size (mm)              Min. Width (mm)

Thermoplastic            90 & under                          300
Thermoplastic             110 & over                       O.D. + 300
RTR                              250 & under                    O.D. + 300
RTR                             300 – 600                           2 x O.D.
RTR                             Over 600                           O.D. + 600
Cast Iron                      All                                    O.D. + 400
Ductile Iron                  All                                   O.D. + 400″

“Depth of trench shall be dug deep enough to provide a cover above the top of the pipe as listed below, and a ground bed of at least 150 mm from the bottom of the pipe.

Type of Pipe           Nom. Size (mm) & Service              Min. Cover (mm)

Thermoplastic              Sewers, gravity flow                          900
Thermoplastic              Press. pipe under 100mm                 600
Thermoplastic              Press. pipe 100mm & larger             900
Thermoplastic                irrigation, under 90 mm size           300 *
Thermoplastic                irrigation, 90 mm & larger              600
RTR                                   Under 150 mm                              600
RTR                                   150mm and larger                        900
Cast Iron soil                                 Typical                              900
Ductile Iron                                   Typical                              900

* 600 mm under paved roads”

  1. In Sabkha areas, the base support layer shall consist of 150mm deep of Class B crushed stone. (Alternatively, a double layer of sandbags may be used for a base support layer, with approval from the Chairman of Plumbing and Utilities Standards Committee).
  2. Base support layers of crushed stone base shall be compacted to at least 95% per ASTM D698.
  3. Clean sand bedding layers shall be 150mm thick and free of debris or rocks.
  4. A non-woven geotextile with a minimum unit weight of 100 g/sq. m shall be placed prior to placing the clean sand, to avoid sand filtration into the crushed stone base.
  5. Clean sand layer shall be compacted to at least 70% relative density per ASTM D4253/4254 or 95% relative compaction per ASTM D698 whichever gives a higher density.
  6. Frequency of Testing shall be as follows: Road base & subbase, One test for every 2000ft2 (180m2) of each lift; Backfill for trenches, One test for every 50 linear feet (15 meters) of each lift; General fill shall have one test performed for every 5000ft2 (460m2) of each lift.