Inspection and Test Plan for LV Cable Pulling ,Termination & Testing
SI No. | Characteristics | Reference Documents | Records |
1 |
Documentation |
||
Method Statements | Execution procedures and instructions approved | ||
Laboratories accreditations | Local normative / Include in Vendor List | ||
Design | Approved Updated Drawings | Applicable Drawings | |
Equipments | Verification of valid updated certificates, calibration and documentations | Normative and standards | |
2 |
Material |
||
Material Reception | Verification of material : – Material according ESP – Vendors supply the required QA/QC documents, tests and cer- Material free of damage and dirt – Handling and transport of material. – Proper storage |
Technical specifications EPC Contract Applicable Law/Regulations | |
3 |
On-Reel Test before Cable Pulling |
||
On-Reel Test before Cable Pulling | Visual / Testing / Metric | IFC Drawing / Cable Schedule | |
4 |
LV Cable Pulling |
||
LV Cable Pulling | – Stub-up, concrete base & trench cleared for cable pulling. – trench size, location, depth and sandbedding verified / Duct bank. – conduit clean and clear before cable pulling. – cable tray assembly / installation / cable tray clean, clear and free from sharp edges. – Source, routing & destination verified. – Type, voltage, size & color coding verified. – Cable pulling tension observed / Bending radius checked. – Segregation and separation of cable checked. – Grouping (where applicable) , phase ordering and dressing. – No physical damage during and after pulling. – Cable Identification tagging. |
IFC Drawing / Cable Schedule | |
5 |
LV Cable Dressing, Splicing & Termination |
||
LV Cable Dressing, Splicing / Termination |
– Check splicing and termination kit materials are correct and approved type. – Cable Dressing. – Cable Gland execution verified and correct size. – Splicing kit/termination kit installation as per manufacturer’s instruction. – Required splicing/termination accessories installed. – Jacket, armour, sheath tightened and as per manufacturer’s instruction. – Proper size of lug and crimping. – Conductor properly supported, tied or clamped. – No physical damage. – Cable Identification tagging / Ferrule. |
IFC Drawing / Cable Schedule | |
6 |
LV Cable Testing |
||
Continuity and Insulation Resistance Testing |
– Correct bolts, hardware installed and suitable to terminals. – Terminal execution/connection according to manufacturer’s instruction and IFC drawing. – Torque test of bolted connection (where applicable). – Bolted connections tightened. |
IFC Drawing / Cable Schedule | |
7 |
LV Cable Final Termination |
||
LV Cable Final Termination | – Correct bolts, hardware installed and suitable to terminals. – Terminal execution/connection according to manufacturer’s instruction and IFC drawing. – Torque test of bolted connection (where applicable). – Bolted connections tightened. |
IFC Drawing | |
8 |
DocumentationFinal Inspection |
||
Documentation Final Inspection |
Visual | IFC Drawing | |
Punchlist close-out | Visual | IFC Drawing |