This article is about ITP Inspection Test Plan for MV Cable Pulling ,Termination & Testing as per international Standard and Codes.
Inspection and Test Plan for MV Cable Pulling ,Termination & Testing
SI No. | Characteristics | Reference Documents | Records |
1 |
Documentation |
||
Method Statements | Execution procedures and instructions approved | ||
Laboratories accreditations | Local normative / Include in Vendor List | ||
Design | Approved Updated Drawings | Applicable Drawings | |
Equipments | Verification of valid updated certificates, calibration and documentations | Normative and standards | |
2 |
Material |
||
Material Reception | Verification of material : – Material according ESP – Vendors supply the required QA/QC documents, tests and certs – Material free of damage and dirt – Handling and transport of material. – Proper storage |
Technical specifications EPC Contract Applicable Law/Regulations | |
3 |
On-Reel Test before Cable Pulling |
||
On-Reel Test before Cable Pulling | Visual / Testing / Metric | IFC Drawing / Cable Schedule | |
4 |
MV Cable Pulling |
||
MV Cable Pulling | -Stub-up, concrete base & trench cleared for cable pulling -trench size, location, depth and sandbedding verified Duct bank -conduit clean and clear before cable pulling -cable tray assembly / installation -cable tray clean, clear and free from sharp edges -Source, routing & destination verified -Type, voltage, size & color coding verified -cable pulling tension observed -Bending radius checked -Segregation and separation of cable checked -Grouping (where applicable) , phase ordering and dressing -No physical damage during and after pulling -cable Identification tagging |
IFC Drawing / Cable Schedule | |
5 |
MV Cable Dressing, Splicing / Termination |
||
MV Cable Dressing, Splicing / Termination | -Check splicing and termination kit materials are correct and approved type -Cable Dressing -Cable Gland execution verified and correct size -Splicing kit/termination kit installation as per manufacturer’s instruction -Required splicing/termination accessories installed -Jacket, armour, sheath tightened and as per manufacturer’s instruction -Proper size of lug and crimping -Conductor properly supported, tied or clamped -No physical damage -Cable Identification tagging -Ferrule |
IFC Drawing / Cable Schedule | |
6 |
MV Cable Testing |
||
Continuity and Insulation Resistance Testing | Visual / Testing / Metric |
IFC Drawing / Cable Schedule | |
DC High- Potential Testing | Visual / Testing / Metric |
IFC Drawing / Cable Schedule |
|
7 |
MV Cable Final Termination |
||
MV Cable Final Termination | -Correct bolts, hardware installed and suitable to terminals -Terminal execution/connection according to manufacturer’s instruction and IFC drawing -Torque test of bolted connection (where applicable) -Bolted connections tightened |
IFC Drawing | |
8 |
Documentation Final Inspection |
||
Final Visual Inspection / Walk through | Visual | IFC Drawing | |
Punchlist close-out | Visual | IFC Drawing |
MV Control Panel of Adjustable Frequency Drive (SAT) Site Acceptance Testing
Methods for Installing Power and Control Cables as per NEC
Inspection Test Plan for Cable Tray and Accessories Installation
Discover more from PAKTECHPOINT
Subscribe to get the latest posts to your email.