This article is about ITP Inspection Test Plan for MV Cable Pulling ,Termination & Testing as per international Standard and Codes.
Inspection and Test Plan for MV Cable Pulling ,Termination & Testing
SI No. | Characteristics | Reference Documents | Records |
1 |
Documentation |
||
Method Statements | Execution procedures and instructions approved | ||
Laboratories accreditations | Local normative / Include in Vendor List | ||
Design | Approved Updated Drawings | Applicable Drawings | |
Equipments | Verification of valid updated certificates, calibration and documentations | Normative and standards | |
2 |
Material |
||
Material Reception | Verification of material : – Material according ESP – Vendors supply the required QA/QC documents, tests and certs – Material free of damage and dirt – Handling and transport of material. – Proper storage |
Technical specifications EPC Contract Applicable Law/Regulations | |
3 |
On-Reel Test before Cable Pulling |
||
On-Reel Test before Cable Pulling | Visual / Testing / Metric | IFC Drawing / Cable Schedule | |
4 |
MV Cable Pulling |
||
MV Cable Pulling | -Stub-up, concrete base & trench cleared for cable pulling -trench size, location, depth and sandbedding verified Duct bank -conduit clean and clear before cable pulling -cable tray assembly / installation -cable tray clean, clear and free from sharp edges -Source, routing & destination verified -Type, voltage, size & color coding verified -cable pulling tension observed -Bending radius checked -Segregation and separation of cable checked -Grouping (where applicable) , phase ordering and dressing -No physical damage during and after pulling -cable Identification tagging |
IFC Drawing / Cable Schedule | |
5 |
MV Cable Dressing, Splicing / Termination |
||
MV Cable Dressing, Splicing / Termination | -Check splicing and termination kit materials are correct and approved type -Cable Dressing -Cable Gland execution verified and correct size -Splicing kit/termination kit installation as per manufacturer’s instruction -Required splicing/termination accessories installed -Jacket, armour, sheath tightened and as per manufacturer’s instruction -Proper size of lug and crimping -Conductor properly supported, tied or clamped -No physical damage -Cable Identification tagging -Ferrule |
IFC Drawing / Cable Schedule | |
6 |
MV Cable Testing |
||
Continuity and Insulation Resistance Testing | Visual / Testing / Metric |
IFC Drawing / Cable Schedule | |
DC High- Potential Testing | Visual / Testing / Metric |
IFC Drawing / Cable Schedule |
|
7 |
MV Cable Final Termination |
||
MV Cable Final Termination | -Correct bolts, hardware installed and suitable to terminals -Terminal execution/connection according to manufacturer’s instruction and IFC drawing -Torque test of bolted connection (where applicable) -Bolted connections tightened |
IFC Drawing | |
8 |
Documentation Final Inspection |
||
Final Visual Inspection / Walk through | Visual | IFC Drawing | |
Punchlist close-out | Visual | IFC Drawing |
MV Control Panel of Adjustable Frequency Drive (SAT) Site Acceptance Testing
Methods for Installing Power and Control Cables as per NEC
Inspection Test Plan for Cable Tray and Accessories Installation