Electrical Engineering

Site Grounding Inspection Points

By PakTechPoint Published Updated 2 min read

In this article
  1. Site Grounding Test Conditions
  2. Site Grounding Inspection Points
  3. Like this:
  4. Discover more from PAKTECHPOINT

Main keywords for this article are 3-point fall of potential method, Site Grounding Inspection Points.

Site Grounding Test Conditions

Site Grounding Inspection Points
Site Grounding Inspection Points

Site Grounding Inspection Points

  • Verify that ground rods are copper-clad steel not less than 0.625” diameter and a minimum of 8’’ length.
  • Verify that CDOT approved other ground rod type if copper-clad steel was not used.
  • Verify that grounding electrode conductor is not less than #6 AWG.
  • Verify that braided ground straps consist of non-insulated tinned copper flat braid wire not less than 0.5” width and 0.07” thick (for bonding between a cabinet frame and busbar only).
  • Verify that insulated grounding electrode conductors are Type THWN with green jacket color.
  • Verify that grounding electrode conductor was installed in a continuous run without splices or joints.
  • Verify that connectors are exothermic weld for below grade connections and areas exposed to moisture.
  • Verify that connectors are UL listed compression connectors for above grade installations and where safety dictates.
  • Verify that ground bus is copper bar stock with stainless steel stand-off brackets and mounting hardware.
  • Measure resistance of the first installed grounding electrode and test with earth ground resistance tester (3-point fall of potential method).  If results exceed 10 ohm, a second grounding electrode needs to be installed.
  • Verify that second grounding electrode is at least one electrode length away from the first grounding electrode and connected via bonding jumper.
  • Measure grounding electrode system resistance with earth ground resistance tester (3-point fall of potential method).  CDOT will accept 25 ohm or less after two grounding electrodes have been installed.
  • Verify that oxidation and antioxidant compound was used at connection points to ground bus.
  • Verify that stainless steel hardware was used and torqued to a specific value based on hardware grade, material, and size.
  • Verify that connections to ground bus utilize a flat washer and Bellville washer for each bolt.
  • Verify that all exothermic welds have slag removed.
  • Verify that testing is performed prior to connecting to utility ground.

Advertisement

Discover more from PAKTECHPOINT

Subscribe to get the latest posts sent to your email.

Share this article WhatsApp LinkedIn Facebook
Advertisement

Leave a Comment