Procedure of Vessel Internal Works

Procedure of Vessel Internal Works

Ventilation System

Ventilation system shall be done using fans/blowers with sufficient capacity. Vacuum mode operation shall be preferred for ventilation, where required force ventilation to vessel top and allow fresh air from the bottom. Distance of the ventilation is also critical as it will obstruct access to the manhole, so careful planning shall be done prior to positioning of the fans/blowers in order to address the air circulation inside the vessel. See following photo.

Ventilation System

Manhole Opening, Inspection and Protection Method

All manhole opening shall be done as per construction and safety procedure. Approved safety permit shall be procured prior to nitrogen gas removal. Inspection of manhole flange serration shall also be done. After inspection of manhole flange
serration, put a rubber cover for protection. See attached following photo. Bolts, nuts and gasket shall be kept for reinstatement.

man hole opening protection

Nozzle Inspection and Protection Method

All equipment nozzles shall be inspected for its flange face serration. Should there be any unacceptable damage, it shall be corrected by re-facing it prior to vessel internal works. Appropriate cover and protection on its nozzle flanges face shall be
done. Notice shall be given to Mechanical Department should there be any piping connections to be made. Blind flanges, bolts and nuts and gaskets of correct material shall be used to cover the nozzles of equipment. Equipment nozzle shall
never be use as support by any piping connections. Gaps shall be made between two connections (equipment nozzle and pipe flanges) until final box up of the vessels and piping works are done. See attached photo.

Nozzle Inspection and Protection Method

Tray Pre-assembling Working Bed

Tray pre-assembling working bed shall be of the same size as the diameter of the vessel involved. Materials to be use on top of the working bed shall be of the same materials of the vessel internal. Carefully pre-assembled the required vessel
internals (level wise) and check precisely that all components are complete and of the correct position as if you installed it inside the vessel. Check also for its cleanliness and if contaminated with rust, clean thoroughly with approved cleaning
method and solvent solution prior to installation inside the vessel. After confirmation of material and cleanliness, carefully install it piece by piece inside the vessel. See attached photo.

Tray Pre-assembling Working Bed

Scaffolding Inside and Outside the Vessel

Scaffolding inside and outside of the vessel shall be done by an approved Scaffolders only. Scaffolders shall install scaffolding with maximum effort not to damage the shell surface of the equipment most especially inside the vessel as it
will result into scratches and will lead to rust development/contamination.

All sharp corners and protruding metal ends of scaffolding shall be adequately covered with rubber. Inside scaffolding shall be installed in such a way that enough working  space is provided for installation of vessel internals. Outside scaffolding shall be installed with enough platform size in front of all manholes for worker’s access during working activities. Safety for all workers inside and outside the vessels shall be given much consideration in the scaffolding erection. A temporary cabinet shall be placed (shall not obstruct manhole access) for safekeeping of personal belongings of workers inside the vessel.

 

Read more

Vessel Internal Components Installation Method

Vessel Internal Components Installation Method

Support Ring Installation and Level Reading Method

Support ring installation shall be done on a level wise stage. Install the support ring precisely on the internal of vessel equipment. Check for the orientation of the support ring. The support ring levelness shall be checked by using a 12mm
manometer hose level or its equivalent.

The measurements for the levelness of the support ring should be checked at a minimum of 5 points, 1 in the middle and
1 at each corner for each pass. Tolerance is ±3mm (vendor requirement). If the tray levelness is over the tolerance value, provide shims on the tray support ring and weld as per Saudi Aramco Specifications (SAES-W-010).

WPS for dissimilar base metals shall be use. Levelness for the outlet weir should be checked at a minimum of 3 points, 1 at each end and 1 at the center. Once it is leveled, marked, weld and tightened the bolt to stabilize its position. It is now possible to start Tray Installation.

Tray Installation

Tray installation shall be done on a level wise stage starting from the lowest level. Components shall be ensured its cleanliness and completeness before installation. Clean the portion of inside shell of dust and other foreign particles.
From the pre-assembled parts on the ground, start to install it on the internal of vessels. Carefully assemble and place the component the same way it was on ground.

Start bolting the components to ensure stability. Once the assembly of tray on the first level is completed, clean the portion of internal surface of shell where the second level of tray may be assembled.Place a sheet of non combustible material on the completed first level tray to ensure its cleanliness of dust and other foreign particles.

Continue doing the same process untill completion of tray installation. Always check and double check the tray identification and orientation to ensure continuity of installation work inside the equipment vessel. Ensure that gaps and spacing  of individuals are correct and is based on the latest IFC drawing.

Structured Packing

Segmented Structured Packing

Check bed height of tower attachment and record the dimension. Prior to put into the tower, do a trial assembly of at least one layer of structured packing on the ground so the workers easily understand the configuration of the packing. A wall wiper banding should be bent in order to as per drawing prior to assemble.
Install the bottom layer on packing support in accordance with drawing as confirming the piece mark and the orientation. Segmented structured packing consists of pre cut multiple sections with a radius on peripheral pieces to conform to the tower wall.
Each section is fabricated from parallel layers of structured packing material with opposing angles of corrugations which are held securely together to form a rigid brick. In order to prevent damage, special care should be taken while handling the sections.
The installation positioning plate is an inverted “L” shaped light thickness metal piece. The peripheral segments are the first sections to be installed on the support grid and slide firmly up against the tower wall. Place the positioning plate against this section and then tap it horizontally along its length to secure the piece in place.

Read more

INSTALLATION OF RECIPROCATING COMPRESSOR- MECHANICAL

This article is about INSTALLATION OF RECIPROCATING COMPRESSOR  and focusing to the engineers, technicians and supervisors. You will find lot of documents related to this article. Just navigate our website  www.paktechpoint.com  and find more articles. Please! Do not forget to subscribe our You tube channel also. Thanks in Advance.

PLEASE SUBSCRIBE OUR PAKTECHPOINT YOUTUBE CHANNEL

INSTALLATION OF RECIPROCATING COMPRESSOR

Please do the initial preparation for work.

Secure work permit and other applicable approved documents prior to work commence.

Tools and equipment shall be made operational and available for use. Ensure tools are color-coded accordingly.

Conduct lifting study & get approved lifting plan accordance with required cases.

Prior to the arrival of equipment on site, Contractor shall review the manufacturer’s requirement and the requirements of this specification regarding on site storage of the equipment. These requirements shall be incorporated to site preservation plan and adhere to in all respects.

Install barricades to confine the area for authorized personnel only.

Foundation for Installation of Reciprocating Compressor 

Confirm acceptances & turnover of civil works foundation/pedestals with a signed copy of works release notice.

After receiving foundation release note, the following points shall be checked.

 Distinct position (center) marking and height (level) marking on the foundation, It will be referred for alignment work of level and position.
 Size and Position of Anchor Hole

Using theodolite establish centerline of the equipment unit. Mark centerline on concrete foundation using paint/ prick punch.

Trace centerlines of foundation bolt holes with reference to gridlines. Check plumbness of anchor bolt.

Clean the surface thoroughly by blowing with oil-free from air compressor.

Center lines lost due to chipping operations will retrace anew.

The elevation of the chipped top foundations shall allow for at least 25 mm of grout under the base plate as per SAES-Q-005 (ARAMCO STANDARD) Concrete Foundation.

Read more

error: Content is Protected.