This article is about Horizontal Distribution Conduit System Installation for Building Premises Distribution System.
Horizontal Distribution Conduit System Installation | Telecommunication
Horizontal Distribution Conduit System Installation
- Verify that for conduits that serve one (1) box, an inside diameter of 1.9 cm. (3/4 in.) or greater is required.
- Verify that ceiling tiles are removable.
- Verify that the height of ceiling tiles are no greater than 3.4 m (11 ft) above the finished floor.
- Verify that conduit runs in the most direct route possible (usually parallel to building lines), with no more than two 90° bends between pull points or pull boxes.
- Verify that conduit runs contain no 90° condulets (also known as LB).
- Verify that conduit runs contain no continuous sections longer than 30 m (100 ft).
- For conduit runs that total more than 30 m (100 ft) in length, ensure that pull points or pull boxes are inserted so that no segment between points/boxes exceeds the 30 m (100 ft) limit.
- Verify that conduit do not runs on top of cellular floor cells.
- Verify that conduit do not runs crosswise to cellular floor cells.
- Verify that conduit do not runs through areas in which flammable material may be stored or handled (Hazardous Classified Area).
- Verify that conduit do not runs over or adjacent to:
– Boilers.
– Incinerators.
– Hot water lines.
– Steam lines.” - Verify that aluminum or thin-walled plastic conduit are not placed in concrete floors
- Verify that the proper capacity for cabling, a one inch (27mm ID) conduit from a terminal or telecommunications room shall not serve more than one information oulet in offices.
- Ensure that conduit bends is long, sweeping bends and shall have a minimum bending radius of ten (10) times the internal conduit diameter.
- Verify if a conduit run requires more than two 90° bends, a pull box between sections with 2 bends or less is provided.
- Verify that all ends of metallic conduit are reamed and bushed.
- Verify if a conduit run requires more than two 90° bends between pull points or pull boxes, then de-rate the design capacity by 15% or use the next larger size of conduit.
- Bushings shall be placed on the ends of metallic conduit to protect cable sheaths from damage.
- Verify that each conduit that enters a TC is terminated near the left corner of the closet to allow for proper cable racking and splicing.
- Verify that each conduit that enters a TC is terminated 10 cm (4 in.) above the finished floor.
- Verify that each conduit that enters a TC is reamed or bushed and terminated as close as possible to the wall where the backboard is mounted (to minimize the cable route inside the room).
- Ensure that all conduits are:
• Clean, dry, and unobstructed.
• Capped for protection.
• Labeled for identification and sealed to comply with firestop requirements. .
• All conduits (end to end) are equipped with a plastic or nylon pull line that has a minimum test rating of 90 kilograms (200 pounds). The end of each pull line shall be secured to avoid loosing the end section.” - Verify that ceiling conduits and cabling are suspended from or attached to the structural ceiling or walls with hardware or other installation aids specifically designed to support their weight.
- Verify that the ceiling conduit runs have adequate support to withstand pulling the cables.
- Verify that the ceiling conduit runs is located 15 cm (6 in.) to 30 cm (12 in.) above the T-bar and have clear vertical space.
- Verify that the ceiling conduit runs have a minimum of 8 cm (3 in.) of clear vertical space from conduits, wires, and cables.
- Verify that the ceiling conduit runs and cables are not resting directly on ceiling panels, framework (T-bars), vertical supports, or other components of the suspended ceiling.
- Verify that the minimum required clearance is maintained between the conduit to avoid electromagnetic interference (EMI). Clearances chall be:
• 1,2 m (4 ft) from large motors or transformers.
• 0.3 m (1 ft) from conduit and cables used for electrical power distribution (220, 120 volts)
• 12 cm (5 in.) from fluorescent lighting. Pathways should cross perpendicular to fluorescent lighting and electrical power cables or conduits.
Standards Codes and References for Horizontal Distribution Conduit System Installation
SAES-T-916, Telecommunications Building Cable Systems.
Telecom Closet / Telecom Equipment Room Size And Location.
Telecommunications Infrastructure Design Process.
ANSI/TIA/EIA 568-B Commercial Building Telecommunications Cabling Standard.
Telecommunications Outside Plant Systems Design SAES-T-938 Download.