INTERMEDIATE TRAY INSPECTION POINTS | TOWER INTERNALS

INTERMEDIATE TRAY INSPECTION CHECKLIST

Information in this paragraph are typical points to check on site during loading. Up-to-date inspection sheets will be provided on site by start-up manager.

INTERMEDIATE TRAY INSPECTION POINTS | TOWER INTERNALS

Following are steps to inspect and install intermediate tray in tower internals.

  1. PANEL INSTALLATION

    1. Container opening / Panel laying down on outside trestles at ground.
    2. Panel punch mark checking & cleanness inspection.
    3. Panel Upper & lower screen inspection at ground.
    4. Panel nozzle closure with plastic caps.
    5. Neoprene sheet installation on panels.
    6. Panel lifting & laying down on beams.
    7. Panel positioning with metal spacers.
    8. Panel rocking detection / Shim plate tack welding.
  2. ROPE PACKING

    1. Panels – Shell – Centre pipe Rope packing.
    2. Tray cleaning.
  3. PANEL SEALING

    1. Clip adjustment & positioning / Tack welding / inspection.
    2. Clip welding / inspection.
  4. BEAM INSTALLATION

    1. Beam laying down on trestles at ground.
    2. Beam punch-mark checking & cleanness inspection.
    3. Main beams installation / positioning / centering.
    4. Main beam levelling / rocking / Shim plate tack welding.
    5. Secondary beam installation / positioning / centering.
    6. Secondary beam levelling / rocking / Shim plate tack welding.
    7. Main beam – Centre Pipe – Axis paint Marking.
  5. INTERNAL PIPING & CENTER PIPE BLANKET INSTALLATION

    1. Internal piping preparation / inspection.
    2. Installation/ bolting.
    3. Centre Pipe Blanket installation.
  6. FIXED THERMOCOUPLE VERIFICATION (BED 1, 6, 11, 13, 18, 23)

    1. Verification of flexible thermocouple in their position.
  7. TRAY CLEANING & FINAL INSPECTION

    1. Tray final cleaning & removal of Neoprene sheets.
    2. Screen vacuum cleaning.
    3. Screen – Clip – Bellows – Beam – Cleanness inspection.
    4. Collecting data for bed volume calculation.
  8. TRAY SIEVE LOADING

    1. Loading Hopper installation / Catapac centering – positioning – testing.
    2. Sieve loading / intermediate inspection / sampling.
    3. Bed levelling / Adjusting sieve quantity / Catapac platform air blowing.

Please check out this related article also: LOWER TRAY INSPECTION POINT | TOWER INTERNALS

TRAY PANEL INSTALLATION

Procedure Hold points
– Preparation
Panels are laid down on trestles at ground. Punch mark & screen status carefully inspected.
Check the inside of the tray panels by removing the plastic cap, blow dry air or vacuum clean if necessary
At ground, all nozzles covered with plastic cap. Neoprene sheets
taped on screen.
Lower & upper screen panel inspection
‘Neoprene sheet taped with adhesive tape
Nozzle covered with plastic cap
Cleanness inside the tray panels
Angle bars welded on trays near the center pipe
Overall Cleanness
Wear shoes protection before starting the tray panel installation to
avoid damaging the sieve and bring dirt inside the adsorbers.
Upper face of beams
Upper face of support rings
Upper face of annular chambers
– Sequence of panel introduction
Axens inspector must be inside before starting the introduction
of the 1 panel.
Follow the sequence carefully for proper positioning on the support
beams.
– Lower panel screen
Before positioning, each lower tray panel screen must be inspected
carefully with a flash light ( check for damages done during handling)
– Flatness and stability of panels
Check the good contact between the panels, the beams and the
support rings.
If there is any rocking, insert and tack weld shim plate on outside
edge of the frame.
Panels 1 A to 8B
– Gap between panels
Install spacers for positioning and maintain the position with screw clamps.
Gap between panels must be 15 mm Maximum.
– Gap between panels and shell
Maintain a minimum gap on shell side for the rope.
At the end of the panel installation, shoes protection can be
removed
Gap between panels and shell must be 10 mm Mini.

ROPE PACKING

General remark:
Because of the poor roundness of the shell, the diameter of the rope to be used shall be adjusted (30, 20, 8mm) according to the gap available especially between the panels and the shell. The rope packing shall be done smoothly to avoid damaging the rope.

Procedure Hold points
– Rope packing :
Rope packing must be done following a specific sequence given by Axens.
Use the recommended rope packing tools.
Check that the rope used for the previous bed is in a good conditions (dry
and clean)
Rope wrapping & status ( clean and dry) & type & diameter
No free space between panels
Last row must be flush to the upper edge of panel frame
– Rope packing between panels
The first row must be packed carefully against the rope arrestor in order to
prevent the rope going through it.
Last row of rope must be flush to upper edge of panel frame.
Gap after rope packing: 15 mm Max between panels
Last row of rope must be flush to upper edge of panel frame.
Gap after rope packing: 15 mm Max between panels
Rope packing between center
pipe and panels
– Rope packing between panels and shell
Install 1 row of rope to compensate the height of rope arrestor.
If clearance between shell and panels is larger than 25 mm, then install
30 mm and 8 mm diameter ropes if necessary.
If clearance smaller than 8 mm, then install 8 mm diameter rope.
Complete the rope filling up to the top of panel frames.
Last row of rope must be properly
Inserted.
– Tray cleaning
All rope debris and dust shall be removed.
Pack the remaining rope care/ ully in a clean and dry plastic bag.
Cleanness
Remaining Rope wrapping status
– Clip position paint marking
As following the clip arrestor arrangement scheme, indicate on both
side of the panel frame the position of the clips
Paint marking on the tray panels

CLIP INSTALLATION

Procedure Hold points
– Clip installation
Position clip according to Axens recommendations (paint marks).
Typical pitch between 2 clips = 500 mm.
Install the clip perpendicular to the frame. If the gap between the clip
and the frame is larger than 3 mm on each side, turn the clip in order
to get 2-3 mm between the clip and the frame to ease the welding
Tack weld.
Location of clips after tack welding
Minimum gap between Clip-screen:
5 mm min.
Clip perpendicular to the frame panel.
Clip position after tack welding
Clip welding Welding quality

TRAY SUPPORT BEAM INSTALLATION

Procedure Hold points
– Preparation
The support beams are laid down on trestles at ground.
Punch mark carefully inspected.
Cleanness (no rust)
Number of support beams
Punch Mark
– Main beam installation
During beam installation, Axens inspector must supervise the
beam installation from inside the tower if possible.
To check level, flatness of the upper surface and alignment use spirit levels (short and long).
In case of beam rocking, shim plates of different thickness must
be used and tack welded on support beam.
Signed up on all checking points with a paint marker as
following Axens marking procedure
Rocking
Centering of the beam inside support (delta max: 1 mm).
Centering of the beam between the 2 supports (delta max: 5mm).
Level (2 directions)Alignment:
– beam upper face with center pipe support ring (delta: 3 mm Max.)
– beam upper face with shell support ring (delta: 3 mm Max)
Checking Marks on the beam, shell & center pipe.
– Secondary beam installation
During beam installation, Axens inspector must supervise the
beam installation from inside the tower if possible.
To check level and alignment use spirit levels.
In case of beam rocking, shim plates of different thickness must be used and tack welded on support beam.
Signed up on all checking points with a paint marker as following Axens marking procedure
Follow the Axens sequence of installation
Rocking
Centering inside support ( delta max: 1 mm)
Centering between the 2 supports(delta max: 5mm with the shortest distance between beam angle and shell).Level (2 directions)
Alignment:
– beam upper face with center pipe support ring ( delta : 3 mm Max.)
– beam upper face with shell support ring ( delta : 3 mm Max)
Checking Marks on the beam, shell & center pipe
– Axis tracing
Trace main beams axis only using a ruler with a paint marker.
Using as reference, on each side of the center pipe, the middle of the
length between the two longest secondary beams, mark up the center
pipe and the shell for further vessel dimension measurement at 700
mm from the screen.
Axis paint marking on Main beam axis, shell & center pipe.

INTERNAL PIPING

Procedure Hold points
Internal piping inspection at ground
Check the punch marking, number and status of the piping at ground
or on the top platform.
Conditions ( clean, dry, no rust, no iron filings)
Protection of the bellows w/ PVC tube
Number, type of the piping
Installation of the piping
Install the piping with final gasket.
Perform a thorough inspection and check all the bellows (alignment, tension).
Bolt and tighten the flanges.
Visual inspection (tension and alignment of bellows)
Flexible hose installed length (welding line to welding line) to be checked to be between 430 and 470 mm.
Bolting Tightened
Verification of the final gasket installation

CENTER PIPE BLANKET INSTALLATION

Procedure Hold points
– Center pipe blanket
Follow the Axens procedure
Bolting of the grip collars (top and Bottom). Tackweld on bolts.
Blanket conditions after installation
No free space at the seam location.

FIXED THERMOCOUPLE VERIFICATION ON BED 2, 6, 12, 14,18, 24

Procedure Hold points
Check any damage on the thermowell
Pack some rope in the nozzle to minimize dead volume
Status of the thermowell
Rope packing in the nozzle

TRAY FINAL CLEANING

Procedure Hold points
– Preparation
Remove the section of ladder present in the bed
Remove all debris and tools. Vacuum clean the neoprene sheets
before removal.
Remove all neoprene sheets and vacuum clean the screen.
Wear shoes protection before starting the tray final cleaning to
avoid damaging the screen
Cleanness before Neoprene sheet Removal
Shoes protection to be worn all the time
Bed free of ladder

TRAY FINAL INSPECTION

Items for inspection : Laser meter, ruler (3m), pen, wrench XX, spirit levels (short & long), flash light, Axens tray doc., small knife

Procedure Hold points
– Adsorber conditions
Dry air must be blown to ensure a dry atmosphere before sieve
loading
Dry air in service
Access to bed during loading
Hoist chain to be removed at bottom
– Ladder Bed free of ladder
– Screen status & slot spacing Slot spacing checking with feeler gauge
– Rope packing Rope packed everywhere
– Clips Position / distance between clip & screen
Welding
– Beam conditions
Walk on it to detect any rocking
Rocking
Level
Axis marking (beam axis)
– Internal piping
Look for any uncompleted work, absence of gasket, damaged bellow.
Bolting (checked with a wrench)
Gasket type
Bellows tension, status of the protection
– Blanket around center pipe Installation & seam quality
– Cleanness
Look for remaining tools, dye stains, welding stains. In case of dust or dirt, ask for more cleaning (vacuum cleaner).
Shell / center pipe
Upper part of beams
Support Ring on center-pipe I shell
Screen surface
– Thermocouple Position

 


Discover more from PAKTECHPOINT

Subscribe to get the latest posts to your email.

Leave a Comment

error: Content is Protected.