LIST OF ACTIVITIES
|
POTENTIAL HAZARDS
|
HAZARDS CONTROL
|
RESPONSIBLE PARTY
|
Planning |
• Unplanned Execution |
- All necessary materials, tools, equipment and certifications or documents must be identified, prepared and provided prior execution and as required by each activities (e.g.,3″ party Certifications, etc.)
- Work permits must be prepared and completed before each conduct of activities.
- Tool box talk meeting discussing all related hazards, risk and control measures as per this document must be done.
- Proper coordination with the Client and other subcontractors must be done accordingly (work interface).
|
Client
Representative,
Project Manager,
CM/Project
Engineer,
Safety Personnel,
QA/QC
Supervisor, |
Mobilization |
• Vehicle poor conditions
• Over speeding
• Improper vehicle parking |
- Only Drivers with SAG valid license is allowed to drive transport vehicle.
- Ensure that the vehicle is properly maintained,
inspected and in good condition.
- Drivers shall abide all the SAG traffic regulations and Client/ Saudi Aramco traffic
requirements at all times.
- Drivers shall not exceed the posted speed limits
- Ensure that the vehicle is appropriate, adequate and sufficient as per the type of
elements to be loaded.
- Seat belts must be properly working and vehicles must have a portable first aid kit and fire extinguisher.
|
Driving Personnel
Site Supervisor
Safety Officer
Foreman |
Lifting and Rigging / Activity Forklift operation (Cable Drum and other heavy materials and equipments) |
• Incompetent crane and rigging
operation
• Unsecured attachments
• Uneven grounds
• Poor condition equipments
• Damage rigging equipments
• Obstructed access ways
• Over speeding
• Unstable and over loading
• Limited visuals (Forklift reversing)
• Carbon Monoxide |
- Obtain and comply with the requirements indicated in a Daewoo applicable Lifting work permit.
- Ensure that the lifting load chart of the crane to be use is provided including the S WL and other credentials of the operators and riggers is attached therewith asrequired.
- Crane Operators and Riggers must be Saudi
Aramco Certified. Inspection of slings, shackle and all the rigging tools and equipment must be done prior to any lifting activity.
- Never exceed the corresponding Safe Work
Load of any equipment as well as the rigging components
- Use of spreader bar is a must to prevent damages to the edges of the units to be lifted. Use of softener is also an option.
- Ensure the ground condition, it must be balance and even and the crane outriggers must be fully extended and touching the ground firmly through a timber sole plate.
- Full time supervision of Supervisor/Project
Engineer/Safety Engineer is required.
- Crane operator are must stay inside the vehicle while operation is on going
- Ensure the area for the units to be located is
properly prepared. Unwanted materials must remove.
- Barricade the work area through isolation by
using warning and danger tapes. Passers-by must be prevented from walking over the area of activity.
- Provide signboards.
- No one is allowed to work under suspended load.
- Ensure the total weight and other significant specification of the material to be lifted. It must be precise and accurate to prevent misinformation.
- In rigging operation, if working above the material to be lifted and the height is more than 1.8 meters that is required to attach the rigging tools, an extra sling belt must be attached to the crane hook to serve as lifeline for the full body harness of the rigger and prevent falling.
- Use tag-line to control the movement of the object.
- Use seat belts
- Equipments must have installed Roll Over Protection System (ROPS)
- Assign flag man in order to assist the forklift operation loading, unloading and transporting of the units
- Records of equipment inspection must be checked to ensure that equipment is properly inspected by an authorized third party certifying body
- Inspect and ensure that the travel route of the forklift is of even ground without any obstructions
- Do not speed up to get the job done faster
- Balance and secured loading of loads.
- Forklift Operator must be Saudi Aramco Certified. Ensure that the forks of forklift will provide sufficient lifting support by ensuring that it will pass through from end to end of a pallet or load to be lifted.
- Slow down, sound the horn at blind corners, doorways and aisles.
- Operate with caution.
|
CM/Project Engineer,
Safety Personnel,
Supervisor, Crane Operator
Rigger |
Scaffolding / Erection / Use
Alteration & Dismantling |
• Incomplete/unstable scaffold
members
• Inadequate fall protection system
• Overloading
• Defective and inadequate
planking.
• Unsafe Access
• Uneven ground and footings
• Scattered tools, material &
debris above platform
• Electrical Power lines and
energized equipment
• Falling Objects |
- Scaffold erection to be undertaken by trained
and certified scaffolders working under supervision of Saudi Aramco certified
Scaffolding Supervisor and approved by an Aramco Certified Scaffolding Inspector if height is above 6 meters.
- Inspection and tagging must be conducted 4.3
prior to usage of any scaffolding.
- Fall protection system must be provided. Top rail, Mid-rail and Toe
boards must be in place and Personal
Fall Arrest System (PFAS) attached
to a secured anchorage point must be
use by workers I .Sm above the
ground. Anchorage point must be
able to withstand 5,000 pounds of
force applied outward or downward.
- Ensure that the scaffolding is able to withstand 4 times the maximum intended load it will carry
- Any gap of 2 feet elevation from ground to access ladder of scaffolding, a step stool or equivalent means must be provided.
- Working platform and access must always be maintained free of debris and tripping hazards.
- Ensure caster wheels are of heavy duty type and locks engaged when in use
- If contact to overhead energized power lines are inevitable, coordinate with the power supplier and request for shutdown and apply the Lock Out Tag Out as per the Daewoo Procedures.
- When working nearby energized equipment, contact the Client and request for shutting down prior execution of work. If shutting down of the equipment is not applicable, safe work plan with the Client is a must to provide in precautionary measures isolating the exposure to electrical hazards is required.
- All tools shall be provided with tag line tied to the working personnel.
- Scaffold components will be lifted using safe techniques (components will not be throw-up to the scaffolder nor to the ground).
- Drop Zones shall be properly barricaded with corresponding sign to avoid other workers from entering.
- Safe means of access/egress to be provided and maintained.
- Unauthorized personnel will be excluded from the area where scaffold erection is being carried out.
- A worker shall be assigned at ground level or near drop zone to restrict other employee from entering at work area.
- Scaffolds must be leveled, rigid, plumb & squared.
|
CM/Project
Engineer
Safety Personnel
Site Supervisor
Scaffolding
Supervisor
Scaffolding
Inspector (>6m
height)
Scaffolding
Erector |
|
• High Weather temperature
• Heat Stress |
- All workers prone to heat stress must be properly informed / oriented about factors that contribute to the illness that it will cause
as well as the control measures to prevent it.
- Environmental conditions must be monitored
(e.g., air temp. relative humidity) and communicated to all expose employees
- Sufficient number and spaced shaded resting
shelters must be provided for workers. It must
be located not exceeding 100m (330ft) away from personnel working or exposed to direct sunlight or direct open brazing flames.
- Provide sufficient number of local ventilation (e.g., industrial fans or portable air movers.
- Portable blowers with built-in air chillers shall be used as needed ( e.g., when confined spaces and enclosed work areas have ambient temp. exceeding 43°C) to provide cooling for confined spaces and similar enclosed work areas.
- Work scheduling could be consider to conduct the activities in the cooler times of the day, especially during the month of Ramadan if it falls on summer.
- Sufficient amount of cooled drinking water must be provided to the workers. And must be located not exceeding I00m (330ft) away from personnel working or exposed to direct sunlight or direct brazing open flames. Workers must be encouraged to drink plenty of water.
- Workers highly prone to heat stress (Brazers) shall be allowed additional break time and water as they deem necessary for their health.
- Personal Monitoring and Buddy System must be implemented. No hot work activity shall be done by an employee in solo or alone.
- Proper PPE must be use (e.g., light colored, light weight, breathable clothing). Use of FRC are required for Brazers, in this case, Safety Personnel assigned together with the supervisor and brazing workers may assess and provide mitigation plans in reducing the high probability of heat stress to occur. Wetted clothing or towels could also be put into consideration.
- Employees must undergo heat stress training.
|
CM/Project Engineer
Safety Personnel
Site Supervisor |
Manual Installations
accessories5.1 Lifting and carrying cable trays, supports, conduit
pipes and accessories. |
- Heavy loads, improper repetition and awkward positioning.
- Ergonomics Hazard
- High temperature and humidity.
- Low visibility inside buildings/facilities.
|
- Prevent awkward positioning such as 5.1.1
& overreaching tilting by providing adequate working platform.
- Wherever possible, a reduction in the 5.1.2
amount of heavy manual handling must be sought by providing adequate mechanical means (e.g., jacks, hand trucks, rollers,
wheelbarrows, etc.,)
- Ensure sufficient ventilation
and 5.1.3 illumination by providing industrial fans and additional lightings complying electrical
safety procedures. (minimum requirements of 50 lux – general construction area lighting, I00 lux general construction plant and shops ( e.g., mechanical and electrical equipment rooms, 30 lux accessways)
- Wear gloves when handling any materials or objects. Where an object requires two or more employees to handle it, one employee should give the direction for lifting and lowering the object in unison.
- All lifting devices shall be kept in good condition. Do not exceed the capacity of any lifting device. Do not move a suspended load over the head of an employee. Riding on a suspended load is prohibited.
- Buddy System must be implemented.
- Ensure clear access.
- Get a good footing and never try to lift anything, which considered too heavy or too bulky.
- Place the feet about shoulder width apart in a comfortable, balanced position, close to the load being lifted.
- Bend the knees and grasp the load.
- Keep back straight — not vertical but straight.
- It should not be arched or bent.
- Take a firm hold on the load with the palms of the hands NOT just the fingers.
- Use gloves to protect against any sharp protruding objects.
- Keep back as straight as possible, tucking chin in to lock spine.
- Lift gradually by straightening the legs – let the strong thigh muscles do the work — not the lower back muscles.
- Do not twist the body or turn one of your feet when lifting.
- If you have to change direction, tum with both of your feet, not your body.
- Avoid lifting or holding above shoulder height and repetitive actions. Take breaks.
- Stack or store between waist and shoulder height.
- When lowering, maintain a good grip and keep the back straight.
- Avoid holding or working in a static work position.
- For Heat Stress comply as per section 4.18 onwards procedures.
|
Safety Personnel, Site Supervisor, Workers |
|
Personnel Fall
from heights
Improper or use of
defective ladders
and working
platfonn |
5 .1.26 Ensure that the elevated working platform
complies with the fall protection system and
in good condition
5.1.27 Guard rails must be complete and secured
clamped
5.1.28 Primary and secondary fall protection system
must be properly installed
5.1.29 Comply as per Sections 31.0 – Working at
Height and 32.0 — Ladders of HSEP-ZP-D
JZR& TP0 1 Rev. 00
5.1.30 Ladders must be properly inspected, in good
condition and use according to its design.
5
.1.31 Straight Ladders use for access must extend 3
feet (Im) to the landing surface, tied and
secured to the structure or the bottom part by
assigning a worker to hold the ladder while it
is in use.
5.1.32 Maintain 3 points contact.
5.1.33 No overreaching, maintain the belt buckle
inside the side railings of the ladders to keep
in balance. |
|
5.2 Installation of transformer, MV (if required) and LV Panels |
- Heavy loads, improper repetition and awkward positioning.
- Ergonomics Hazard.
- Falling Objects.
- Personnel Fall from heights
- Improper or use of defective ladders and working platform.
- Improper location of units.
|
- (Comply as per applicable controls, required stated in 5.1 activity)
- Installation be done in accordance to applicable Daewoo standards and procedures.
- Install disconnection switches that are capable of being lock and tag.
- Ensure that the designated location and specification complies as per the approved IFC drawing.
- Ensure proper supervision and monitoring of an Electrical Engineer/ Supervisor.
|
Electrical Engineer,
Supervisor, Electricians |
5.3 Cable pulling, laying, testing and termination. |
- Hazards Identified in 5.1 and 5.2.
- Static friction.
- Sharp edges.
- Improper termination.
- Tripping/ rolling off cable drum.
- Electrical shock.
|
- (Comply as per applicable Hazard control stated in 5.1 activity)
- Provide any means of reducing the static friction by using rollers, lubricants and the likes, to prevent workers in applying
excessive force.
- Identify and remove sharp edges to prevent cuts and damages to cables and workers.
- Cable drums must be secured by wooden
wedge when stacked, isolated and barricaded.
- Use project/ construction approved jacks and spindle.
- Cable spindle must be positioned or set-up on level and firm ground
- Keep away from nip/pinch & crush points.
- Comply with the material handling and stacking control measures / requirements.
- Cable dressing must be removed immediately to maintain good housekeeping.
- Ensure that insulation testing apparatus are inspected, calibrated and properly insulated.
- Ensure that the activity be done only by the authorized person such as Electricians and properly monitored by Electrical Engineer/Supervisor.
|
Electrical Engineer,
Supervisor, Electricians |