MODIFICATION THREADED JOINT PROCEDURE (UNDER GROUND VENT PIPE)

1. PURPOSE
2. SCOPE.
3. REFERENCES.
4. RESPONSIBILITIES.
5. MAN POWER.
6. TOOLS AND EQUIPMENT.
7. MODIFICATION PROCEDURES.
8. QUALITY CONTROL.
9. SAFETY PRECAUTION.
10. ATTACHMENT.

MODIFICATION THREADED JOINT PROCEDURE (UNDER GROUND VENT PIPE)

1.0 PURPOSE

This method of statement shall provide minimum Guidelines to carry out the Modification of Threaded joint(Seal welding-Underground Vent Pipe) activities, for plants and refinery projects in accordance with Project Drawings and Project Specifications.

2.0 SCOPE

This procedure applies to Modification Threaded joint (Seal welding-Underground Vent Pipe) for plants and refinery projects.

3.0 REFERENCES

SAES-L-350 Construction of Plant Piping.
SAES-W-011 Welding Requirements for On-Plot Piping.
SAES-W-012 Welding Requirements for Pipelines.

SAES-H-200 Storage, Handling and Installation of Pipe Externally Coated Pipe.
SAES-L-110 Limitation of Pipe Joints and Component.
SAES-S-070 Installation of Utility Piping System .
SAEP-1142 Welding Requirements for Pipelines.
SAES-A-206  Positive Material Identification.
SAES-A-301 Materials Resistant to Sulfide Stress Corrosion Cracking.
01-SAMSS-024 Pipe Handling and Nesting.
SCHEDULE “Q” Quality Requirements.
SAEP-351 Bolted Flange Joints Assembly.
SAES-L-109  Selection of Flanges, Stud Bolts and Gaskets.
ASME B1.20.1  Pipe Threads, General Purpose..

ASME B31.3 Process Piping.
ASME B31.4 Pipeline Transportation System for Liquid Hydrocarbons and Other Liquids.
ASME B46.1 Surface Texture (Surface Roughness Waviness, and Lay).
ASME B16.20 Metallic Gaskets for Pipe Flanges.

Latest Approved Drawing

4.0 RESPONSIBILITIES

4.1 Construction Manager shall be responsible for the overall implementation of this procedure and shall appoint personnel to undertake periodic audit to ensure this procedure is being complied with.
4.2 Health Safety & Environment (HSE) Supervisor/officer shall be monitoring according to HSE regulation and requirement.
4.3 Material Controller shall be responsible for ensuring that all materials are stored and transferred to the custody of the Construction Contractors in a clean and dry condition, suitably protected to ensure ingress of debris and moisture is prevented.

4.4 Field Superintendent shall be responsible for ensuring that all Field Supervisors and Contractor personnel are aware of the requirements of this procedure and for monitoring its implementation at site.

4.5 Field Supervisors shall be responsible for the detailed day-to-day operation of the procedure. They shall be required for regular inspections in line with the agreed quality plans and random inspections of Construction Contractors operations to ensure the requirements are being successfully implemented.
4.6 QA/QC Manager has the responsibility to:
4.6.1 Review of all request including Daily Welding Inspection Report.
4.6.2 Managing welder qualification.
4.6.3 Managing control system.
4.6.4 Managing of quality control
4.6.5 Managing inspection and test with regard to support installation

5.0 MANPOWER

5.1 The Piping Superintendent shall control the overall activity he shall be directly reporting
to the Construction Manager. The basic manpower under him shall consist but not limited to the following:
5.1.1 Piping Foreman
5.1.2 Pipe Fitters
5.1.3 Welder

5.1.4 Helper
5.2 QC Inspector
5.3 Safety Officer

6.0 TOOLS AND EQUIPMENT

6.1 Tools and equipment needed should be in good condition and must be checked by Supervisor/ Safety Officer prior to use in the construction area. These includes but not limited to:
6.1.1 Paint brush / roller
6.1.2 Welding machine
6.1.3 Straight edge
6.1.4 Magnetic/spirit level
6.1.5 Grinder
6.1.6 Steel brush
6.1.7 Welding outfit

7.0 MODIFICATION PROCEDURE (Underground Vent Pipe)

7.1 Prepare materials needed for the job.
7.2 All materials or tools must be in good condition.

7.3 Modification Threaded joint (Seal welding)

7.3.1 Underground connection will be removed by loosening the threaded joints.
7.3.2 Grinding the removed threaded part of the pipe connected to the flange.
7.3.3 Flash grinding inside of flange connected to the pipe as per Fig. 7.1 Modification Threaded joint(Seal welding)
7.3.4 Prior to welding check for cleaanliness of inside piping, cleanliness of surface, alignment of piping and root face for any deficiencies.
7.3.5 After alignment and levelness is accepted, removed foreign matter from the welding joint prior to fit-up weld.
7.3.6 The welding shall be a fillet weld going from the outer diameter of the female part, and it should be smooth with slight concavity as allowed by ASME B31, to the male part covering all exposed thread without undercut.

Fig 7.1 Modification Threaded joint (Seal welding)

Fig 7.1 Modification Threaded joint (Seal welding)
7.3.7 Welding can be done by either GTA W weld process or SMAW process
7.3.8 After acceptance of fit-up proceed to seal welding as per approved WPS.
7.3.9 All weld joint shall be marked and approved in the latest IFC Isometric DWG.

7.4 Touch-up paint

7.4.1 Surface preparation and coating shall be in accordance with the SAES-H series standards, related 09-SAMSS series specification and this project specification. The work shall result in properly coated surfaces free from pinholes, voids, skips, runs, sags, thin spots, dirt and abrasive inclusions, and other evidence of poor workmanship.

7.4.2 Prior to any mechanical/hand tool cleaning; oil, grease, paint and other surface contaminants shall be removed from steel.
7.4.3 All touch-up and repair of coated surfaces at construction site shall follow Table A of specification of S-000-13A0-001 (Supplementary Specification for External Coating)

8.0 QUALITY CONTROL

8.1 Quality Control personnel will be assigned to ensure the quality control and assurance requirement of the project.
8.2 Quality Control Inspector shall coordinate with the other inspectors to conduct inspection as required in SATIP.
8.3 QC Inspector shall be responsible to conduct all required inspections/documentations and to ensure that all applicable requirements, codes, and standards are complied with.
8.4 QC to utilize the applicable SAIC for every activity.
8.5 Calibration shall be done as required for all machines and tools that are going to be used in the work in accordance with Schedule Q.

9.0 SAFETY PRECAUTIONS.

9.1 Approved work permit shall be obtained prior to the start any painting works.
9.2 Work execution shall be carried out in accordance with this method of statement.
9.3 Painting crew must carry out a safety risk assessment prior to the start of any new activities.
9.4 The necessary manpower inclusive of supervisory staff, tools, equipment, materials, and other resources required must be made available and ready to use.

9.5 Workers shall be provided with and wear their PPE’s needed for work.
9.6 Only Saudi Aramco certified man lift operator(s) shall be allowed to operate the man lift equipment.
9.7 Sufficient lightings shall be provided if work is done at night time.

10.0 ATTACHMENTS

10.1 Job Safety Analysis (JSA)
10.2 Approved WPS