This test is related to quality management system requirements and documentation requirements as per Schedule Q. Following multiple choice questions we prepared for all QA, QC engineers, Quality professionals and PIDs who are working on Aramco projects or other international projects. These questions also necessary who are attending CBT test of Aramco or other major companies.
Schedule Q Question Answers – 2.
According to the Quality Management System requirements, who shall implement a Quality Management System in accordance with ISO 9001?
Answer:C
CONTRACTOR shall implement for this Contract a Quality Management System in accordance with the latest version of ISO 9001.
2. 2. According to the requirements, in case of conflict between ISO 9001 and the Schedule “Q” of the Contract, which requirements shall have precedence?
Answer: B
In case of conflict between ISO 9001 and this Schedule, the requirements of this Schedule “Q” shall have precedence.
3. According to the requirements, who shall plan, organize, control, and execute all WORK in accordance with CONTRACTOR’s Quality Plan(s), Inspection and Test Plans (ITPs) and documented procedures?
Answer: C
CONTRACTOR shall plan, organize, control, and execute all WORK in accordance with CONTRACTOR’s Quality Plan(s), Inspection and Test Plans (ITPs) and documented procedures.
4. When should CONTRACTOR submit its narrative project specific Quality Plan including Construction Inspection & Test Plans (ITPs) for review and approval?
Answer: B
CONTRACTOR shall submit the Quality Plan including Construction ITPs no later than twenty one (21) calendar days after the effective date of the Contract.
5. According to the requirements, what must CONTRACTOR do before commencing fabrication on any item required to have ITP’s?
Answer: B
CONTRACTOR shall not commence WORK prior to COMPANY approval of the applicable ITP.
6. According to the requirements, what should CONTRACTOR include if adopting the COMPANY Typical Inspection Plans (SATIP) and COMPANY Inspection Checklists (SAIC)?
Answer: C
CONTRACTOR shall include a list of applicable SATIPs for execution of the scope of the WORK in accordance with Schedule “B” of this Contract.
7. According to the requirements, when should CONTRACTOR modify its Quality Plan(s) and ITPs or SATIPs to reflect significant changes identified by CONTRACTOR or COMPANY?
Answer: A
CONTRACTOR shall modify its Quality Plan(s) and ITPs or SATIPs to reflect any significant changes and resubmit within seven (7) calendar days.
8. According to the requirements, where should the latest revision of CONTRACTOR’s Quality Manual and applicable Quality Plans be available?
Answer: D
The latest revision of CONTRACTOR’s Quality Manual and applicable Quality Plans shall be available for COMPANY’s use at the CONTRACTOR’s design, procurement, fabrication, and installation or construction locations.
9. According to the requirements, what version of ISO 10005 should CONTRACTOR follow for Quality Plans?
Answer: A
CONTRACTOR shall prepare Quality Plans in accordance with the latest version of ISO 10005.
10. According to the requirements, what must CONTRACTOR submit for COMPANY approval a minimum of 30 days prior to the start of any activity not supported by SATIP(s)?
Answer: A
CONTRACTOR shall prepare an Inspection and Test Plan(s) and supporting checklists and submit to COMPANY for approval a minimum of 30 days prior to the start the activity.