SEALING OF VENT HOLES ON HANDRAILS AFTER INSTALLATION

1.0 PURPOSE
2.0 SCOPE
3.0 APPLICABLE DOCUMENTS
4.0 RESPONSIBILITIES
5.0 MANPOWER
6.0 TOOL’S AND EQUIPMENT
7.0 METHODS/ WORK PROCEDURE
8.0 PAINTING REPAIR WORK
9.0 QUALITY CONTROL.
10.0 SAFETY PRECAUTION
11.0 ATTACHMENT

SEALING OF VENT HOLES ON HANDRAILS AFTER INSTALLATION

1.0 PURPOSE

1.1 The purpose of this method statement is to describe the sequence of work and safety precautions to be observed to ensure that the sealing work of vent holes on handrails after installation shall be performed in accordance with the project specification and safety standard of commercial buildings, plants and refinery projects.

2.0 SCOPE

This method statement will describes the works processes in sealing of vent holes on handrails of steel structure at commercial buildings, plants and refinery projects after installation using epoxy steel resin since seal welding after installation is not practical (12-SAMSS-007, sec. 6.2.6.8). The procedure to be applies to all vent holes on handrails at different elevation. Execution of work shall be carried out safely and in accordance with the relevant project specifications and safety standard.

3.0 APPLICABLE DOCUMENTS

3.1 ARAMCO project specifications and standard.

3.1.1 SAEP-302 Instruction for obtaining a waiver of a Mandatory Saudi ARAMCO Engineering Requirements.
3.1.2 SAES-M-001 Structural Design for Non-building structure.
3.1.3 SCHEDULE Q Saudi ARAMCO project Quality Requirements.
3.1.4 12-SAMSS-007 Fabrication of Structural and Miscellaneous Steel.
3.1.5 12-SAMSS-008 Erection of Structural and Miscellaneous Steel.
3.1.6 G.I 0008_001 Safety Requirement for scaffolds.
3.1.7 SAUDI ARAMCO Construction Safety Manual.
3.1.8 SAES-B-067 Safety Identification Standards and Safety Colors.

3.2 Industry Codes and Standards

3.2.1 AISC-303-05 AISC code of standard Practice for steel buildings and bridges.
3.2.2 AIC-360-05 AISC Specification for structural steel building (March 9, 2005} Page 145 (Chapter M Fabrication, Erection and Quality Control)
3.2.3 PIP STS05120 Fabrication of Structural and Miscellaneous steel.
3.2.4 PIP STS05130 Erection of Structural and Miscellaneous steel.
3.2.5 ASTM A385 Standard Practices for Providing High-Quality Zinc Coatings (Hot Dip)
3.2.6 SAES-H-001 Coating Selection and Application Requirements for Industrial Plants and Equipment

3.3 Inspection and Test Plan/ Method Statement.

3.3.1 SAIC-H-2027 Surface Preparation for Liquid Coating Systems.
3.3.2 SAIC-H-2029 Inspection of Primer Coating (Prior to Top Coating).
3.3.3 SAIC-H-2031 Inspection of Top Coat(s) of Liquid Coating System.

4.0 RESPONSIBILITIES

4.1 Construction Manager shall be responsible for implementing HSE matter and to study, analyse and schedule all construction activities with his department to include manpower and equipment line up
as well as other possible resources required for the successful implementation of the construction and sealing work activities. Study all aspects of work procedure as per technical Scope of work.
4.2 The structural supervisor shall study and review all necessary documents for the sealing works of vent holes on handrails in his area to include, technical scope of work, specification and construction procedure.
4.3 Structural foreman shall be responsible for the direct work supervision at site to ensure that the sealing works of vent holes on handrails will be performed in accordance with Technical Scope of work, project specification and standard.
4.4 QC Inspector shall be responsible of monitoring and inspection of the work and ensure that the work will be performed in accordance with Technical Scope of work, project specification and standard.
4.5 Safety Supervisor/Officer shall be responsible of monitoring safety aspects and ensuring that the work will be done in accordance with Safety Standard Procedure. He shall give reminders or advise to the workers to do the activity safety.

5.0 MANPOWER

5.1 Manpower will consist of the following, but not limited to as listed below.
5.1.1 Structural Supervisor
5.1.2 Structural Foreman

5.1.3 Painter
5.1.4 Helper
5.1.5 Steel Workers
5.1.6 Safety Supervisor/Officer
5.1. 7 QC Inspector
5.1.8 Scaffolder

6.0 TOOLS AND EQUIPMENT

6.1 Tools and equipment needed should be in good condition and must be checked by structural Supervisor and Safety Officer prior to use in the construction area. These Includes but not limited as Below.
6.1.1 Electric Grinder
6.1.2 Sandpaper
6.1.3 Paint brush

7.0 METHODS/ WORK PROCEDURE

7.1 Sealing Procedure

7.1.1 Surface to be repair and sealing must be clean, dry and free of oil, grease or wax.
7.1.2 Remove cap and puncture seal of both resin and hardener.
7.1.3 Squeeze equal amounts from both tubes. Mix throughly until a uniform color is achieved. must be used within 4 minutes.
7.1.4 Apply the mixture and fill the holes.
7.1.5 Mixture will become warm while it sets. Recommended for applications about 50F (10C)
7.1.6 After hardening file smooth surface and touch up with paint.

APPLICATION OF EPOXY STEEL RESIN ON VENT HOLES
APPLICATION OF EPOXY STEEL RESIN ON VENT HOLES

APPLICATION OF EPOXY STEEL RESIN ON VENT HOLES

8.0 PAINTING REPAIR WORK

8.0.1 Repair Procedure for atmospheric Coatings. Please follow the surface preparation and application requirements in the coating selection and application requirements for industrial plant and equipment and the manufacturer’s technical data sheet.
8.0.2 Touch up painting shall be ensure the surface preparation and application requirements in the applicable coating selection and application requirements for industrial plant and equipment and the manufacturer’s technical data sheet. (SAES-H-001 para 9.6).

9.0 QUALITY CONTROL

9.0.1 Q/QC inspectors shall conduct the inspection, documentation
9.0.2 QA/QC inspectors shall record and file all the necessary documents duly signed and approved by the company representative in all aspects of work.
9.0.3 Re-inspection of materials that already modified such as; Surface preparation prior to application of touch up painting.

10.0 SAFETY PRECAUTION

10.1 Work Execution shall be carried out in accordance with this method of statement.
10.2 All crew must carried out a safety risk assessment prior to start of any new activity.
10.3 The necessary manpower inclusive of supervisory staff, tools, equipment, materials, and other resources is required must be available and ready to use.
10.4 Workers should wear their PP E’s always.
10.5 Good housekeeping must be maintained in the duration of works.
10.6 Safety supervisor/Officer and Engineer shall monitor compliance of entire working crew for the safety procedure until the work is fully completed.

11.0 ATTACHMENT:

► JOB SAFETY ANALYSIS
► MATERIAL SAFETY DATA SHEET
► TECHNICAL DATA SHEET

 


Discover more from PAKTECHPOINT

Subscribe to get the latest posts to your email.

Leave a Comment

error: Content is Protected.