QC Notes Lecture_8_Aramco Standard Electrical and Instrument Question Answers Part_3

QC Aramco Standard Electrical and Instrument Question Answers

QC Aramco Standard Electrical and Instrument Question Answers

1.            Explain procedure related to Quality Control?
Ans:   The quality procedure is the series of steps taken to maintain the quality standard as per the adopted standard and other specific.
2.            What do you know about NEC, NEMA VE1, NEMA VE2, NEMA RN?
Ans:   NEC – National Electrical Code earlier used to be published under the statutory body of NFPA since 1897, from 2005 edition it is categorized as an internationally  accepted method inspection procedure guidelines covering all most all the field related to Electrical, Instrumentation and Communication Engineering.
NEMA VE1 – National electrical manufacture association VE1
NEMA VE2 Deals with cable tray installation specification
3.            What are the articles refereed during carrying out the following activities?
(1)  Grounding. (2) Installation of cable Tray. (3) Fire alarm System Installation. (4) Installation Instrument Cable Tray etc,
Ans:   (1) Grounding  Article 250 (Chapter IX for instrumentation), (2) Installation of cable tray
Article 392, (3) Fire Alarm System Article 760, Installation of instrument cable tray article 727.
4.            What is Duct bank?
Ans:   It is concrete poured structure with conduits laid inside by maintaining certain specified elevation as per the requirements for the laying of cable through this enabling protection, support and safety to the cable.
5.            What would be the thickness of the top layer of a Duct Bank and color?
Ans: 5 mm and Red Dye.
6.            What is the purpose of using paint/dye on top layer?
Ans: To give an anticorrosive protection, top layer painting is provided.
7.            What are types of conduits used in electrical and instrumentation wiring circuits?
Ans:   Rigid Metallic Conduit (RMC), Intermediate Metallic Conduit (IMC), Rigid Nonmetallic
Conduit (RNC).
8.            What are the differences between a JB (Junction Box) and Terminal Box?
Ans:   The purpose of JB (Junction Box) is used as a linkage between one or more inlet and one or more
outlet. Whether terminal box has inlet on or more but out let may be one for earthen or it may not be. JB can be used in between the routing for providing support and extra opening but TB is used as Termination means at the end of the routing.
9.            What is ‘termination’ related to construction industry?
Ans:   Termination is widely used term in case of construction industry. For electrical and instrumentation work this is used for make the routing as a complete one.
10.         What is the impulse line?
Ans:   It is line rather tubing connection made from the source (flow pipeline or vessel) to the transmitter (sensing device) to create the feasibility to the transmitter to sense the flow and to generate equivalent electrical signal to get the indication of the status of the system working.
11.         What is the check list?
Ans:   It is the list of sequential activities to be performed by any QC Inspector during inspection of any activity performed by construction. It is made separated with distinguished activities for each construction activity.
12.          What is punch list? What is requirement of making a punch list?
Ans:   It the list generally identified as RA 60B, which is used at the time of finalization of any activity. Means every activity should be stamped with a final and foolproof documentation which shows the clear evidence of the all completed job. It is always signed by QC to ensure the maintainability of the quality aspect of the job performed.
13.         What is the role of QC during shut down?
Ans:   QC has the major role to be played at the time of shut down. It is the responsibility of QC to officially hand over any completed project to the client with all the documentations to be provided with the real completed project. This including the records of completion (activity wise) areas with limitations as shown in punch list, the processing and final inspection test report of the actual functioning of the project by making it operational.
14.         What do mean by Hazardous and Non Hazardous area?
Ans:   The area classification is done as per area wise risk involvement (environmental). The area with maximum percentage of risk in function any system is known as hazardous area (NEC Art 500 – 510).
15.         How  are the hazardous and non hazardous areas classified?
Ans: Hazardous and non hazardous areas are classified according to the classifications and zones.
16.         What is the Expansion joint? What should be the standard gap maintained in expansion joint?
Ans:   It I the breathing space provided to accommodate the expansion of horizontal cable tray to suit with different climatic condition by maintaining a standard length wise distribution.
According to NEMA VE2 it is after every 20 meter with a spacing (expansion joint) of 25 mm to be maintained. It sometimes differs, but should not be more for the horizontal length of the cable try.
17.         How the metallic cable trays grounded?
Ans:   Metallic cable tray shall be bonded at both end points and minimum of every 25 meter local ground grid or ground electrode or to structural steel bonded to local ground grid or ground electrode.
18.         How the metallic conduit grounded?
Ans:   grounded at both end points by bonding to grounding conductor, grounded metal enclosure or to grounded metal cable tray by using approved grounding clamps.A grounding bushing must be used with PVC coated conduit.
19.         How many connection points required for equipment ground?
Ans: a)
For equipments like (motor, generators and transformers) which operated at 1000 v or greater shall have two connections to supplementary electrode.
b)   If the motors, generators and transformers operating at nominal voltage 480 v shall have a minimum of one connections to supplementary grounding electrode.
20.         What type of conduit is used in duct bank?
Ans: Duct bank consists of either hot-dip galvanized rigid steel with PVC coated or PVC conduit, encased in concrete.

Read more

QC Notes Lecture_8 Aramco Standard Electrical and Instrument Question Answers Part_2

Aramco Standard Electrical and Instrument Question Answers Part_2

Aramco Standard Electrical and Instrument Question Answers Part_2

1.            What are inspection points for a cable tray installation?
Ans:   Material check as per approved spec, size and type, tray’s hook-up, proper distance structure, tray to tray i.e. power/control/and signal/low voltage and high voltage, support and fixed strongly not shaking.
2.            What are inspection points for field instruments with impulse tubing?
Ans:   Materials inspection as per approved spec material, type and size, Installation as per Hook-up, check line route to avoid any obstruction, check tube bending, and check tube support, compression fitting or ferrules, and then pressure test (hydrostatic test) shall be done.
3.            What are inspection points for a cable laying?
Ans:   Material inspection as per approved materials, types and size, meggering, cable routing  drawing, completion of cable route ( tray, conduit or trench etc ) and cable numbering (Tag), cable bending, use or proper tools and equipment for cable pulling.
4.            What are inspection points for Junction Box and Marshalling cabinets?
Ans:   Material Inspection, type, size as per approved specification, installation hook up for frame, bracket or stands, fixed properly means shaking free, Name Plate, and tag no.
5.            What are standards methods or ferrules addressing to and from a Junction Box?
Ans:   For to side only terminal’s address required which shall be close to terminal either side and complete information shall be of from side after or before as per left and right side.
6.            What is final RFI? When it shall be raised up?
Ans:   When the QA/QC department of contractor is satisfied that the work detailed in the construction RFI is completed, then request shall be submitted for inspection to the client QA/AC department.
7.            What is schedule Q?
Ans:   Schedule Q is an attachment to the contract, which is the provision of Quality Assurance and Control, Inspection and test plan.
8.            What are the various levels of Inspection? Explain?
Ans: They are as following.

Level of Inspection for Materials:

A: Level 0 – Documents requirements only, no Inspection.
B: Level 1 – Inspection prior to shipping.
C: Level 2 – Minimum requirements, pre-inspection meetings, one  or more unspecified “in progress” surveillance visits.
D: Level 3 – Same as level 2, except that “in progress” surveillance inspection shall be in regular basis.
E: Level 4 – Resident Inspection Continuously monitor the work.

Level of Inspection for construction phase:

A: Hold Point (H): The inspection activities will not proceed without the presence of inspection.
B: Witness Point (W): Inspection activities can be proceeding after issuing RFI.
C: Review (R): Verification of documentation (NMR) on its correctness as per spec and approved drawings.
D: Surveillance (S): Inspection has right to conduct random inspection of works.
E: Inspection (I) / Perform (P) / Test (T): construction can be proceeding to next phase without client inspection.
9.            What is ITP’s? What are Hold and Witness Point?
Ans: ITP mean Inspection and Test Plan, details of work scope and required types of inspections.
Hold Point (H): is the level of inspection that client inspection must require through RFI and can’t be preceded until inspection is done by client.
Witness Point (W): is the level of inspection that inspection activity can be preceded without client inspection or if client is not available as per RFI Timing.
10.         What is RFI? When an RFI will be raised?
Ans:   Request for inspection (RFI), RFI shall be raised only when the status of the preliminary inspection is satisfactory, and the works (items) are Hold or Witness Point.
11.         What is Cable tray and how is it identified separately for Electrical and Instrumentation?
Ans:   Cable tray is the device used to provide support and protection to the laid cable in side the building or outside pipe rack.
12.         What is Calibration and what is process calibration?
Ans:   Checking / testing the equipment for its accuracy and serviceability are known as calibration.
Process calibration means carrying out calibration activity by following the adopted authorized method linked with standardization.
13.         What is the loop and how is the loop folder made?
Ans:   Loop is the electro-mechanical presentation of the circuit concerning to flow of liquid or gas, alarm system, control valve operation and other specific for which field installation instrument involvement is considered. There are certain condition and requirements to be fulfilled to complete the loop check.
The list of attachments including drawing, check list and punch list and other listed documents are arrange in folder (loop wise) for having an easy access to carry out the loop check and final hand over of the project. That folder with all possible documents is known as loop folder.
14. What is the specialty rather characteristics of loop check? How do you come to know that loop check is completed
Ans:   a. Loop check is a clear blue print of a successful system functioning (activity wise).
b. This emphasis the serviceability of each instrument installed either in field or inside the building,
c. This exposes also the limitation of some systems functioning as per the attached filled punch list,
d. One of the ready documents for final hand over of a project on completion,
e. It is always two team’s operation-one will be on field and the other will be in the control room, After every successful completion of loop check it is marked with Red Colored Label bearing the date
of the loop check and the witnessing parties initial.
15.        What is the standard and what is the Standardization?
Ans:   The standard means the authenticated documented instruction to be followed during execution
of any specific project for which it is made.
Standardization means the method of execution of certain standard, which is specific to the one
or more related activities in a project execution process.

Read more

QC Notes Lecture_8 Aramco Standard Electrical and Instrument Question Answers Part_1

Aramco Standard Electrical and Instrument Question Answers Part_1

Aramco Standard Electrical and Instrument Question Answers Part_1

1.            What is QA/QC?
Ans:   QA/QCmeans, “Quality Assurance / Quality Control” The purpose of this (QA/QC) is to
establish the sequence of requirement for the quality of material, quality of
works, its inspection, and records
2.            What is the MMG Quality Control Management System?
Ans: ISO 9001 ~ 2000
3.            What is the Quality Control?
Ans:   Quality Control “Those activities and techniques used to achieve and maintain the quality of product, process or service”.
4.            What is Quality Control Plan?
Ans:   Quality Plan “Document Specification which procedures and associated resources shall be applied by whom and when to specific project, product, process or contract”.
5.            What is non-conformity?
Ans:   Non-conformity“Non-fulfillment of requirement”. (Complete failure of a system, or controls, which result in completely unsatisfactory goods or services being provided).
6.            What is the Specification?
Ans: Governing Document Acceptance Criteria.
7.            Who are the responsible for Quality?
Ans: Everybody within all organization.
8.            What is the basic responsibility of a QA/QC personal?
Ans: To ensure execution of works and comply fully as per standard and approved specs.
9.            What is the basic required document for a QA/QC personal?
Ans:   The basic required documents for a QA/QC personal are as following.
ITP (Inspection Test Plan): To conduct the quality check (Inspection of Witness, Surveillance and Hold Point) etc.
RFI: To conduct the inspection of completed work.
QR (Quality Record): To maintain the quality records of completed works etc.
NCR: To issue warning in case of serious violation of standard.
WP (Work Procedure): Standard procedure to execute the works.
P & ID: As a reference to ensure that the work is as per standard drawing.
MTC: To ensure that material comply the PES standard specs.
Calibration Report: To ensure parameters are function checked as per IDS.
PP (Project Plan): To ensure that the instruments are installation as per P & ID and PP as per convenience.
Hook-up: To ensure that the remote connection of pneumatic is done correctly.
Wiring Diagrams: To ensure that wiring is done correctly ILD: To ensure that the sequential wiring is done correctly.
IDS/ISS: To ensure that the instruments comply with the basic requirement.
QCO: To issue a warning in case of little violation and observation.
DR: Discrepancy Report.
10.         What are QA/QC’s ITP and QCP? Give brief?
Ans:   ITP: This procedure informs about the kinds of quality check (surveillance, inspection, witness or hold pints) means quality of works is being done in proper sequences.
QCP: This procedure addresses the activities and requirement in details.
11.         What is NCR? Why does it need for a QA/QC personal?
Ans:   NCR means Non-Compliance Report, QA/QC personal has reserve the right to issue a warning if the contractor doesn’t comply or violate with the standard procedure.
12.         What is the general procedure (WP)?
Ans:   The general sequence of activities will be as follows:
Receiving Drawing and Documents.
Reproduction of Drawings.
Issuing of drawing to site.
New-Issuing new Revision.
Shredding drawings.
Transmittal of redlines to Client (As-built).
Restricted access to the DCO.
Work Permit prior to starts the works.
Records.
13.         What is redlining? Brief its color coding?
Ans:   In case of any change occur to the standard approved drawing while the project is being constructed or tested the relevant drawing will be “redlined”. Following color coding shall be used for this purpose.
Red: If any addition required from the drawing.
Green: If any Deletion is required from the drawing.
Blue: If any comments is added.
14.         What is difference between inspection (Surveillance), witness and Hold point?
Ans:   Inspection: Work can be execute without client’s inspection and it can be inspected some part of them
if it is required.
Witness: Work can be executed, without client inspection and then it can be inspected upon the completion of work.
Hold Point: Work can’t be executed without client inspection.
15.         What is difference between hazardous and non-hazardous Areas?
Ans:   Hazardous: A hazardous location is defined as an area where a potential for fire or explosion exists
due to the presence of flammable gases, liquids or vapors, combustible dusts or fibers and flying in sufficient quantities to produce an explosion or ignitable mixture.
Non-hazardous: An area where non risk of presence of any kinds exposition.

Read more

error: Content is Protected.