This article is about Backbone Conduits System Installation of Building Telecom Distribution System as per International Codes and standards.
Backbone Conduits System Installation | Telecom System
Backbone Conduits System Installation
- Verify that ceiling tiles are removable when installation of conduits for backbone system is planned.
- Verify that conduits junction points are installed where they are fully accessible from floor area below and safe for cable installations and changes.
- Verify that the height of ceiling tiles are no greater than 3.4 m (11 ft) above the finished floor when installation of conduits for ceiling distribution system is planned.
- Verify that conduit runs contain no 90° condulets (also known as LB).
- Verify that conduit runs contain no continuous sections longer than 30 m (100 ft).
- For conduit runs that total more than 30 m (100 ft) in length, ensure that pull points or pull boxes are inserted so that no segment between points/boxes exceeds the 30 m (100 ft) limit.
- Bushings shall be placed on the ends of metallic conduit to protect cable sheaths from damage.
- Verify that conduit runs in the most direct route possible (usually parallel to building lines), with no more than two 90° bends between pull points or pull boxes.
- Verify that conduit do not runs through areas in which flammable material may be stored or handled (Hazardous Classified Area).
- Verify that conduit do not runs over or adjacent to:
– Boilers.
– Incinerators.
– Hot water lines.
– Steam lines.” - Verify that each conduit that enters a TC is terminated 10 cm (4 in.) above the finished floor.
- Verify that each conduit that enters a TC is reamed or bushed and terminated as close as possible to the wall where the backboard is mounted (to minimize the cable route inside the closet).
- Ensure that the radius of a conduit bend is at least 10 times the diameter of the conduit.
- Verify if a conduit run requires more than two 90° bends, a pull box between sections with 2 bends or less is provided.
- Verify if a conduit run requires a reverse bend (between 100° and 180°), a pull point or pull box is provided at each bend having an angle from 100° to 180°.
- Verify that a minimum of 2-three inch conduits is provided when linking two telecommunication closets (TC) to each other. Larger conduits are to be provided when required by the service demands.
- Verify that overhead conduits entries into the TC shall protrude into the closet a distance of 5 cm (2 in) at a minimum height of eight (8) feet.
- Ensure that all conduits are:
• Clean, dry, and unobstructed.
• Capped for protection.
• Labeled for identification.” - Verify that ceiling conduits and cabling are suspended from or attached to the structural ceiling or walls with hardware or other installation aids specifically designed to support their weight.
- Verify that the ceiling conduit runs have adequate support to withstand pulling the cables.
- Verify that the ceiling conduit runs is located 15 cm (6 in.) to 30 cm (12 in.) above the top surface of the cable tray side rail.
- Verify that the ceiling conduit runs have a minimum of 8 cm (3 in.) of clear vertical space from conduits, wires, and cables.
- Verify that the ceiling conduit runs and cables are not resting directly on ceiling panels, framework (T-bars), vertical supports, or other components of the suspended ceiling.
Standards Codes and References for Backbone Conduits System Installation
1. SAES-T-916, Telecommunications Building Cable Systems.
2. Commercial Building Standard for Telecommunications Pathways and Spaces.
Telecom Closet / Telecom Equipment Room Size And Location
Telecommunications Infrastructure Design Process
J-STD-607-A Commercial Building Grounding (Earthing) and Bonding Requirements For Telecommunications
ANSI/TIA/EIA 568-B Commercial Building Telecommunications Cabling Standard
Telecommunications Outside Plant Systems Design SAES-T-938 Download.