Installation Of Work Area Outlet Boxes of Building Distribution System

This article is about Installation, Inspection Of Work Area Outlet Boxes of Building Premises Distribution System, bicsi tdmm, ansi tia 569 d telecommunications pathways and spaces pdf, bicsi telecom room standards, bicsi tdmm 14th edition pdf free download, bicsi standards, telecommunication room requirements, tia 569 standards and tia 569 c.

Installation Of Work Area Outlet Boxes of Building Distribution System

Installation Of Work Area Outlet Boxes

  1. Verify that telecommunications outlets installations in a dry-wall, plaster, or concrete block wall is at least 100 mm square by 57 mm deep (4 in. square by 2 1/4 in. deep).
  2. Verify that outlet boxes are not placed back-to-back that will allow noises to be transmitted between rooms and possible transmission of heat and fire during a fire. Always offset the box locations and interconnect them with conduit.
  3. Verify that cover plates for wall-mounted outlets have two connector openings.
  4. Verify that cover plates for wall-mounted outlets are installed on all outlets boxes.
  5. Verify that wall outlets are securely mounted at least 38 cm (15 in.) above the finished floor or a minimum of 150 mm above desk tops, where it is necessary to locate the outlet behind a desk location.
  6. Verify that wall outlets are placed where they are accessible and allow for the equipment service cord to readily connected.
  7. Verify that outlet boxes are covered with an outlet face plate and identified for telecommunications use only.
  8. Verify that each work area outlet is cabled directly to a TR.
  9. Verify that work area outlets are located where the cable required to reach work area equipment will be no more than 5 m (16 ft.) long.
  10. Verify that horizontal cables are terminated with a standard telecommunications outlet connector connected to a 4-pair 100 ohm balanced category 6 or higher.
  11. Verify that work area is located so that the combined length of cables and line cords used to connect equipment in the work area and TR, plus the patch cable, does not exceed 10 m (33 ft.).
  12. Verify that the outlet meets the standard interface and reliability requirements of the specification IEC 60603-7.
  13. Verify that connections that provide electrical connections between 100-ohm UTP cables shall meet the requirements of ANSI/TIA/EIA-568-B.2 or ISO/IEC 11801 Ed.2:2002.

Standards Codes and References for Installation Of Work Area Outlet Boxes

1. EIA-310-D Standard.
2. SAES-T-795, Communication Facility Grounding System dated 27 February, 2007.
3. SAES-T-916, Telecommunications Building Cable Systems.

Telecom Closet / Telecom Equipment Room Size And Location

Telecommunications Infrastructure Design Process

J-STD-607-A Commercial Building Grounding (Earthing) and Bonding Requirements For Telecommunications

ANSI/TIA/EIA 568-B Commercial Building Telecommunications Cabling Standard

Telecommunications Outside Plant Systems Design SAES-T-938 Download.


Discover more from PAKTECHPOINT

Subscribe to get the latest posts to your email.

Leave a Comment