PIPE SUPPORT FABRICATION PROCEDURE | METHOD STATEMENT

1.  SCOPE

2. REFERENCE
3. DEFINITION
4. RESPONSIBILITY
5. MATERIIAL RECEIVING, STORAGE OF PIPPE SUPPORT
6. PIPE SUPPORT FABRICATION
6.1 Fabrication Work Flow
6.2 Material Marking & Identification
6.4 Material Cutting
6.5 Fit-Up & assembly of pipe supports
6.6 Welding
7. HANDLING AND CONTROL OF PRE-FABRICATED SUPORTS
8. 0 STORAGE
9. INSPECTION
10.0 RELEASING PIPE SUPPORT
11.0 DOCUMENTATION
12.0 SAFETY

Attachment 1 Risk Assessment for Support Fabrication Work Shop

Attachment 2 Support Fabrication Shop Layout Drawing
Attachment 3 General Notes
Attachment 4 Support Material

Attachment 5 Scope of Material Supply
Attachment 6 Support Selection Criteria
Attachment 7 Index
Attachment 8 Daily Fit-up Inspection Report
Attachment 9 Daily Welding Inspection Report
Attachment 10 Paint Request List (Support)

PIPE SUPPORT FABRICATION PROCEDURE | METHOD STATEMENT

1. SCOPE

This procedure applies to all work for fabrication and installation of pipe supports in fabrication shop for Plants and Refinery Projects.

2. REFERENCE

The piping support work shall strictly  conform to the Applicable  Codes,  Standards  and project specifications.

ASME B 31.1 Power Piping

ASME Section V Non- destructive  Examination

ASME B 31.3  Process Piping

ASME Section IX Welding & Brazing Qualification

ASME D 1.1  Structure Welding Code

SAES-A-206  Positive Material  Identification

SAES-L-105  Piping Material  Specifications

SAES-L-110  Limitations on Pipe Joints and Components

SAES-L-132 Material  Selection of Piping System

SAES-L-310  Design of Plant Piping

SAES-L-350  Construction of Plant Piping

SAES-M-001  Structural  Design Criteria for Non-Building Structures

SAES-W-011 Welding Requirements for On Plot Piping

SAES-W-016 Welding of Special  Corrosion — Resistant Materials

01-SAMSS-010 Fabricated Carbon Steel  Piping

12-SAMSS-007 Fabrication of Structural and Miscellaneous Steel

3. DEFINITION

4. Responsibility

The following GIWI  personnel shall be involved and responsible for the activities incorporated  in this method statement and to ensure that all quality aspects are adhered to:

  • Project Manager
  • Construction Manager
  • QA/QC Manager
  • QC Supervisor
  • Piping/Structural  Engineer
  • QC Inspector (s)
  • Structural  Foreman

4.1      Project Manager shall  be responsible for the overall project control activities pertaining to this project

4.2     Construction Manager shall  be responsible for the implementation of this procedure that shall maintain the required quality level at each stage of fabrication.

4.3     QA/QC Manager shall  be responsible in  providing technical assistance to  construction project management as necessary to initiate quality enhancement and resolve quality problems throughout the organization.  Monitor,  provide technical assistance and resolve all quality related problems with the activities of the construction.

4.4     QC Supervisor shall  perform the assigned quality assurance and quality control and inspection activities and assist the QCM. Arrange for Welder Qualification Test and issue qualification certificate to the qualified welders.  Review WPS and PQR for the said activities of the project. Take regular field patrol to assure that welding quality exercised by eligible welder is maintained through overall welding activities and that the welding work strictly adheres to the job requirements. Against the non-conformance,  if any found during the patrol,  issue an instruction to take a corrective action.

4.5     Piping/ Structural Engineer(s) shall  be responsible for the execution of correct working techniques with strict adherence to this method of statement and reference documents.

4.6     Structural  Foremen shall be directly responsible for the Quality maintained by the workmen under them. They shall confirm that latest drawings, specifications, grades of materials, correct tools and equipments,  etc.  are used.  They shall also guide the workmen in the interpretation of drawing/documents so that the work is carried out in the correct sequential  manner,  meeting the various in process inspection activities.

4.7     The Welding Supervisor/Foremen  shall  be responsible for deploying qualified welders. They shall also be responsible for ensuring that the welders withdraw electrodes as per Consumable method of statement.

4.8     QC inspectors/Welding  inspectors shall be responsible for carrying out the in  process inspection, visual  inspection and relevant tests as per ITP’s.  They shall also be responsible for maintaining the documentation and records of inspection.

4.9     Material  Receipt,  Storage of Pipe Support

4.9.1      The Material  Controller shall  receive the raw materials for the pipe support.

4.9.2     All the material will be stored in safe/secure area.

4.9.3     All the materials to be stored in a planned manner so as to easy identification of materials and issue.

4.9.4     Materials up on receipt shall  be checked for quantity by ware house personnel.  QC inspector to conduct material  receiving inspection against the purchase order,  size, quantity,  material specification and material test certificate and heat number when applicable.

4.9.5     Make sure all the raw material are properly marked and recorded with its applicable identification  marked and code numbers as per project requirements.

4.9.6     Pipe support shall be placed on wooden dunnage /pallets to prevent direct contact with the ground.

4.9.7     Stainless steel  materials placed on pallets shall  be free of carbon steel  nails and galvanized wire etc.

4.9.8     Segration of Material as per Specification  Material  in  Lay down Area as per SAES

5. Pipe Support Fabrication

5.1      Fabrication Work Flow

Pipe Support Fabrication

5.2 Material  Marking & Identification

5.2.1      Stainless steel shall  not be marked by stamping,  but may be marked using a Vibrator-Etch tool or chemical  composition acceptance marker.

5.2.2     Paints or inks may be used for marking of supports

5.2.3     Certified chloride-free marking or color coding has water soluble chloride content below 50 ppm (measured after drying) for stain steel materials.

5.2.4     Color coding for support material shall  be done as mentioned below:

Carbon Steel  – No color

LTCS   –            Orange

Alloy (P11)  –   Dark Blue

Alloy (P22)  –   Green

Stainless Steel  (304/304L) –   No Color

Stainless Steel  (321) –            Pink

Monel                      –              Yellow

5.3     Material  Cutting

5.3.1      No flame cutting is allowed on Stainless steel  materials..

5.3.2     Power grinding wheels or high speed cutting wheels and or brushes which   have been used for carbon steel shall not be used for the fabrication of stainless steel  materials.

5.3.3     Carbon steel  materials may be cut by mechanical or thermal  means.

5.3.4     Cutting shall  be made with suitable allowance taken into account for shape of connections and shrinkage due to cutting and welding.

5.3.5     The roughness of  cut surfaces and occasional  notches on edges shall  be removed by machining or grinding.  Cut surfaces and edges shall  be left free of slag.

5.3.6     Before cutting,  suitable material traceability and mark-up of cutting limits shall be done on each part of materials to be cut.

5.3. 7     Contours of all weld end preparation shall  be smooth without any rough edges.

5.4     Fit-Up and Assembly of Pipe Support

5.4.1      Pipe supports shall  be fabricated in accordance with the pipe support drawing.

5.4.2     All the cut materials are checked against approved Drawings and its item  number.

5.4.3     If components are fitted using layouts or fixtures,  it shall  be checked by the QC Inspector with the applicable drawings.

5.4.4     After the fit-up,  dimension and squareness shall be check by the QC Inspectors.

5.4.5     After completion of fit-up,  each support shall stencil with a unique mark to make it traceable to the corresponding spools as per isometric drawing.

5.4.6     The piping are not used to support other pipes and structures without an appropriate analysis.

5.4. 7     Longitudinal weld joints of full encirclement sleeves are provided with 16 GA  back-up strips prior to welding.

5.4.8     The corners of the saddle pads or reinforcing pads have rounded corners.

5.4.9     The edges of all tightly contacting surfaces on the fabricated structural supports (saddle type,  Ring Girder, etc.) are completely seal welded.

5.4.10   All welds of pipe supports to the pipe wall are continuous with smooth finish.

5.4.11    Minimum fillet weld size is 3/16 inch  (5 mm) for structural welds.   (Seal welds may be 1/8 inch  (3 mm) minimum fillet weld.)

5.4.12   Wear pads are installed at each support of Piping in  hazardous services where condensation can form on the pipe, or operating within 30 m of the sea.   Excluded from this requirement are low pressure systems with  hoop stress at design pressure below 20% of Specified Minimum Yield Strength (SMYS) of the pipe.

5.4.13   Type and/or classification of  pipe supports installed on the line conforms with the detailed design drawings and/or the Project Pipe Support Schedule.

5.4.14   Pipe supports are in full  contact with supports that carry the load.   This applies to the fit-up of wear pads,  segmental saddles and full encirclement sleeves to the pipe.

5.4.15   Structural  steel  pipe used for dummy legs  have open ends sealed to prevent internal corrosion.

5.4.16   A 6 mm weep hole is drilled for all dummy supports located   near the base plate for all vertical dummy supports, and near the run pipe at 6 o’clock position for all  horizontal dummy supports.

5.4.17   Additional dummy leg supports other than those in the design drawings are installed  only without prior review and approval  by Saudi Aramco SAPMT or CSD.

5.5    Welding

5.5.1      Fit-up and welding of all  Pipes support materials and components for fabrication system shall be performed in accordance with approved WPS.

5.5.2     Welding shall be done for joining support members, fitting and other components unless otherwise specified on the approved design requirements.

5.5.3     Oil,  moisture,  rust, scale, sand,  paint,  metallic coatings,  or other foreign  matter shall be removed from the weld surface of adjacent base metal  prior to welding,  including any such coatings on temporary attachments or supports.

5.5.4     All the welds shall be made by qualified welders.

5.5.5     Each welding pass shall  be thoroughly cleaned of slag & other foreign  matter before the next pass is deposited.

5.5.6     All slag, flux, and spatter and any stray arc strikes shall  be removed from the completed weld and surrounding area.

5.5. 7     Stainless steel and nonferrous materials shall be cleaned with grinding wheels or stainless steel  brushes not previously used on other materials.

5.5.8     Stainless Steel Area Isolated for Support Fabrication at Shop  No.1  see Attached shop Layout Drawing

5.5.9     Rejected welds shall  be repaired in accordance with the welding procedure,  by qualified welders as per Approved Welding Procedure Specification  (WPS).

6. Handling and Control of Pre-fabricated Supports

6.1         After completion of pre-fabrication, the supports shall be cleaned and free from weld spatters, arc strikes and foreign materials on the surface of the supports.

6.2        Marking / Identification of supports,  Permanently Mark or Stamp with Stenciled / Hard Punching System and Barcode shall at top of base plate one place of each support.

6.3        Upon completion of fabrication, supports shall  be inspected and released for painting or storage,  in accordance to Inspection and Test Plan.

6.4        No supports should be released from the fabrication shops to laydown yard,  painting or site before being fully inspected and released by the QC department.

7. Storage:

7.1         Pipe supports shall  be stored in their designated area in accordance with area identification coding.

7.2        Pipe supports shall  be laid  on wooden sleepers or other suitable material above ground level.

8. Inspection

8.1         Inspection will be carried out in accordance with approved fabrication drawings.

8.2        All welds shall  have 100%  visual  inspection  performed as per ANSI/AWS D1 .1.  In addition, any arc strikes,  gouges,  and other indications of careless workmanship (such as surface porosity) shall be removed by grinding.

8.3        For any ‘Hold’ or ‘Witness’ points of the Contractor and/or Company,  Construction shall issue Forecast for Inspection as per the form attached. This shall  be followed by Application for Inspection by QC Dept.

9. RELEASING OF PIPE SUPPORTS

9.1         After required inspection  has been done and accepted documentation shall be prepared, completed  by the QC inspector prior to release the pipe support.

9.2        The QA/QC inspector shall  prepare the pipe support release sheet for painting.  See Attachment: 9

10. DOCUMENTATION

10.1       Upon completion of pipe support fabrication and/or installation, all the reports shall  be documented by the QC Inspector.

11. SAFETY

11.1       Piping support fabrication and erection / installation will  be undertaken in accordance with the Project Safety Manual.

11.2      All necessary PPE will be provided and worn,  in accordance with the Project Safety Manual.

11.3      All lifting equipment & accessories shall  be certified for their capacity and validity by Third Party which shall be color-coded

11.4      All electrical equipment shall  be properly ground and color-coded.

11.5      All the workers must use their safety equipments and PPE’s.

11.6       Welding generators shall  be ground.

11. 7 Ensure gas cylinders are stored vertically and tied up with chain.  Ensure stickers on gas cylinders with date of filling and inspection.

11.8       Oxy-Acetylene cylinder carriage shall have partition.

11.9       Flash back arrestor shall be installed  near cutting torch.

11.10     Piping Fabrication shops and site will be kept in a clean and tidy manner. Attachment 1-Details of Full  Encirclement Sleeves and Saddle Pads

11.11     All workers must be provided Trainings for Hot works,  lifting,  Manual  Handling, fire watch, TSTI  and electrical  safety respectively.

11.12    Job Supervisor or lead  man should have a clear understanding of the job procedure and its related hazard to communicate with  his co workers and labors.

11.13     Emergency contact numbers should be provided inside fabrication workshop and First Aid kit should be available at site all the times to provide first aid in case of any injury or accident.

11.14     Proper ventilation for the workers shall be provided during the hot summer season to minimize the chances of heat stress and other heat related illnesses.

11.15    Water stations shall  be provided with cold water to maintain the hydration level of the workers during hot environment inside fabrication workshop.

11.16    Auto machines shall only be operated by trained and competent person. The picture of the competent person shall  be displayed near the machine to check if any unauthorized workers not operate machines.

11.17     Signage and poster shall  be displayed inside fabrication workshop to create a safe environment for the workers.

11.18    Adequate fire extinguishers shall  be provided inside fabrication workshop to control  initial fire hazards.

  1. Risk Assessment for Support Fabrication Work Shop.
  2. Support Fabrication Shop Layout Drawing.
  3. General Notes.
  4. Support Material.

  5. Scope of Material Supply.

  6. Support Selection Criteria.

  7. Index.

  8. Daily Fit-up Inspection  Report.

  9. Daily Welding Inspection  Report.

  10. Paint Request List (Support).

 

 

 

 

 

 

Leave a Comment

error: Content is Protected.