UPPER TRAY INSTALLATION NOTES | TOWER INTERNALS

Information in this paragraph are typical points to check on site during loading. Up-to-date inspection sheets will be provided on site by start-up manager.

UPPER TRAY INSTALLATION NOTES | TOWER INTERNALS

There are following installation notes and inspection points for Upper Tray of tower internals.

  1. UPPER TRAY PREPARATION BEFORE INSTALLATION

  2. Catapac removal and packing in dedicated boxes.
    Catapac Trolley A & B removal.
  3. PANEL INSTALLATION

  4. Panel laying down on trestles at ground.
  5. Panel punch mark checking & cleanness inspection.
  6. Panel Upper & lower screen inspection at around.
  7. Panel nozzle closure with plastic caps.
  8. Neoprene sheet installation on panels.
  9. Panel lifting & laying down on beams.
  10. Panel positioning with metal spacers.
  11. Panel rocking detection / Shim plate tack welding.
  12. PANEL FIXING

  13. Panel Bolting.
  14. ROPE PACKING

  15. Panels – Shell – Center pipe Rope packing.
  16. UPPER TRAY SEALING

  17. Welding of Seal plates on panel frame.
  18. Welding of Seal Angles plates on welding rings of shell and center pipe.
  19. INLET BOX DISTRIBUTOR INSTALLATION

  20. Upper tray clearing out.
  21. Storage of manifold piping inside tower through top manhole.
  22. Inlet box distributor installation with gasket (scaffolding).
  23. UPPER PIPING MANIFOLD INSTALLATION

  24. Upper piping positioning / tack welding.
  25. Upper piping manifold welding / dye checking.
  26. Center pipe connection installation.
  27. Upper tray cleaning.
  28. CENTER PIPE / UPPER MANIFOLD PIPING / UPPER TRAY TESTS

  29. Center pipe leak test.
  30. Upper manifold piping and upper tray mechanical / leak tests.
  31. CLIP INSTALLATION

  32. Clip adjustment & positioning / Tack welding / inspection.
  33. Clip welding / inspection.
  34. EQUILIBRIUM DEVICE INSTALLATION

  35. Equilibrium device installation / inspection.
  36. TOP FLANGE INLET INSTALLATION

  37. Inlet box distributor cleaning.
  38. Top flange inlet insertion / bolting.
  39. TOWER FINAL CLOSURE.

  40. Final inspection.
  41. Top manhole closure.

LOWER TRAY INSPECTION POINT | TOWER INTERNALS

INTERMEDIATE TRAY INSPECTION POINTS | TOWER INTERNALS

TRAY PANEL INSTALLATION

Procedure

Hold points

– Preparation
Remove Catapac from platform, Trolley A & B. All panels must be clean, dry, free of rust. All nozzles covered with plastic cap and
adhesive tape. Splash plate in place installed at ground. Blank off
sample points and equilibrium device nozzle with blind flange and new gaskets.
Dry air in service
Panel conditions at ground
Panel nozzle covers
Gasket type
– Cleanliness
During panel installation, avoid any sieve surface disturbing and ensure
there is no foreign material falling down into the sieve bed.
Remove tape/cap covering threaded holes just before panel positioning. Leave the piece of rope until stud bolt screwing.
Upper face of beams
Upper face of support rings
Upper face of annular chambers
hreaded holes (main beams and
secondary beams)
– Panel lower screen
Before positioning, each panel lower screen must be inspected carefully
with a flash light ( damages done during handling)
– Flatness and stability of panels
Check the good contact between panels, beams and support rings.
If there is any rocking, insert and tack weld shim plate on outside edge
f the frame.
Panel 1A to 8B
– Gap between panels
Install spacers for positioning and maintain the position with clamps.
Gap between panels must be 15
mm max.
– Gap between panels and shell
Maintain a minimum gap on shell side for the rope.
Gap between panels and shell must be 10 mm min.

TRAY PANEL FIXING

Procedure

Hold points

– Preparation
Once all panels are properly installed, clear one by one the tap hole for stud bolt. Clean the tap hole blowing dry air.
Panel positioning especially
around bolting slots.
Cleanness of tap holes
Cleanness of stud bolt/ nuts
– Stud bolt screwing
Once a tap hole is clear and inspected, start screwing stud bolts. In the
event that bolting is not possible, check the cleanness or try another stud
bolt.
Stud bolt must be entirely screwed up (tips should not be higher than
frame upper edges to allow seal plate welding).
Stud bolt height within frame
– Bolting
Install washer and bolt the nut maintaining the bolt from its tip. Tackweld
bolt and nut.
Bolt tightening
New washers to be used

ROPE PACKING

Procedure

Hold points

– Rope packing :
Rope packing must be done following the attached procedure.
Wrapping & condition (clean and dry)
& type & diameter
Quality of Rope cutting ( cut clean
through)
No free space
– Rope packing between panels
The first row must be packed carefully against the rope arrestor in order to prevent the rope going through it.
Last row of rope must be flush to
upper edge of panel frame.
Gap after rope packing :
15 mm Max
– Rope packing between panels and center pipe
Install 1 row of rope to compensate the height of rope arrestor.
If clearance between center pipe and panels is larger than 15 mm,
then install 30 mm and 8 mm diameter ropes if necessary.
If clearance smaller than 8 mm, then install 8 mm diameter rope.
Rope packing between center pipe
and new angle plates
– Rope packing between panels and shell
Install I row of rope to compensate the height of rope arrestor.
If clearance between shell and panels is larger than 15 mm, then install 30
mm and 8 mm diameter ropes if necessary.
If clearance smaller than 8 mm, then install 8 mm diameter rope.
Complete the rope filling up to the top of panel frames.
Last row of rope must be
properly
Inserted.
– Rope packing around stud bolt
Fill all space around stud bolt
Packing all around stud
bolts.

UPPER TRAY SEALING: SEAL PLATE & SEAL ANGLE PLATE WELDING

Procedure

Hold points

– Seal cover plate welding on panel frame
Follow typical sequence of tack-welding: tackweld point pitch= 150 mm
Then continuous welding to tight the tray
Dye test checking
– Seal angle plate welding on center pipe and shell welding ring
Follow typical sequence of tack-welding: tackweld point pitch= 150 mm
Then continuous welding to tight the tray
Dye test checking

UPPER PIPING MANIFOLD INSTALLATION

Procedure

Hold points

– Preparation
Identify marking on pipes before mounting. Remove all nozzle covers.
New gasket to be installed
– Center pipe connection Gasket type
Bolting tightness
– Tray Cleaning / scaffolding dismounting

Remove scaffolding, vacuum clean all tray surface

Cleanliness

INLET BOX DISTRIBUTOR INSTALLATION

Procedure

Hold points

– Preparation
Clear out all tray surface and vacuum clean all dust on shell. Use air
extractor during dust removal.
Inspect upper manifold piping at ground. Store all big pieces of piping
manifold inside the tower on upper tray.
Install scaffolding.
Cleanliness of shell and tray.
Piping condition
(cleanliness, rust free, dry).
– Inlet box distributor installation
Position inlet box distributor on the flange under the feed inlet.
Install with appropriate gasket (150# RF W.N. flange).
Tighten bolting.
Cleanliness
Gasket type and positioning
Inlet box orientation
Bolting tightness

CENTER PIPE/ UPPER MANIFOLD PIPING/ UPPER TRAY TESTS

Procedure

Hold points

– Center pipe leak test
Follow AXENS’s procedure
– Upper tray/ manifold piping mechanical/ leak test
Follow AXENS’s procedure

EQUILIBRIUM DEVICE INSTALLATION

Procedure

Hold points

Gasket positioning
Gasket type
Bolting tightness
Piping condition (cleanness, rust free, dry
Flange cleanness
– Equilibrium device installation / bolting Gasket type
Gasket positioning
Bolting tightness
Bolting on lugs
-Top head flush inlet connection (2 in. ) Piping assembly after tack welding.
Dye check
Welding quality
Gasket type
Gasket positioning
Bolting tightness
-Sampling connection (3/4 in.) Piping assembly after tack welding.
Dye check
Welding quality

TOP FLANGE INLET 16″ INSTALLATION

Procedure

Hold points

– Preparation
Vacuum clean from outside the inlet box distributor. Clean, brush rust if any on the top inlet flange.
Inlet box distributor cleanness
Top flange inlet cleanness
– Top flange inlet insertion / bolting Gasket positioning
Gasket type
Bolting tightness

FINAL INSPECTION I TOWER FINAL CLOSURE

Procedure

Hold points

– Final inspection Cleanliness
Gaskets installation
Sample connections
-top manhole closure Gasket position, type