This article is about Orifice Plate/Flow Nozzle Commissioning Checklist, How to check orifice place? Orifice Flow Meter Installation Guidelines, Flow Meter Upstream Downstream Lengths, Orifice Plate Flow Direction, Ultrasonic Flow Meter Installation Guidelines, Orifice Plate Sizing Calculation Excel, Flow Meter Installation Rule of Thumb, Flow Meter Installation Details.
Orifice Plate/Flow Nozzle Commissioning Checklist
Followings are commissioning checklist points for Orifice Plate or Flow Nozzle before system energization.
- Verified per specification sheet.
- Meter run:
- Installed facing right direction.
- Proper upstream/downstream straight pipe meter run.
- Straightening vanes installed.
- Orifice plate:
- Stamped correctly.
- Orifice bore diameter verified with micrometer.
- Installed correctly.
– Sharp edge upstream and identification markings on tab in proper direction. - Maintenance accessibility.
- Junior orifice seal installed and plate bolted down.
- Senior orifice cranking mechanism in working order.
– Plate and gasket installed.
- Flow nozzle:
- Stamped correctly.
- ID plate marked “top” is at top of the pipe run.
- ID plate data is LEGIBLE from the top of the pipe run when facing the flow direction (From this perspective, the right hand pipe tap is the high pressure tap.)
- Tubing as per instrument pneumatic hookup drawing.
- Pressure sensing line from correct side of orifice plate.
Following are more commissioning checklist for Electrical and Instrumentation.
Control Valve Commissioning Checklist
Switch Valves, TSA, and PSA Valves Commissioning Checklist
Pressure Transmitter Commissioning Checklist
Temperature Transmitter (Filled System) Commissioning Checklist
Differential Pressure Transmitter Commissioning Checklist
Displacement Level Instrument Commissioning Checklist
Multipoint Recorder Commissioning Checklist
Orifice Plate/Flow Nozzle Commissioning Checklist
Analyzers Commissioning Checklist
Machine Controls Commissioning Checklist & Instrumentation
Vibration Monitors Proximity/Inertia Commissioning Checklist
Surge Control System Commissioning Checklist
Thermocouple RTD and Well Commissioning Checklist
Alarm Switches Commissioning Checklist
Locally Mounted Controller Commissioning Checklist
Panel Controller Pneumatic/Electronic Commissioning Checklist
Panel Controller Pneumatic/Electronic Commissioning Checklist
Signal Modifiers Electronic and Pneumatic – Commissioning Checklist
PLC | DCS | Power Supply Systems Commissioning Checklist