INSTALLATION OF RECIPROCATING COMPRESSOR- MECHANICAL

This article is about INSTALLATION OF RECIPROCATING COMPRESSOR  and focusing to the engineers, technicians and supervisors. You will find lot of documents related to this article. Just navigate our website  www.paktechpoint.com  and find more articles. Please! Do not forget to subscribe our You tube channel also. Thanks in Advance.

PLEASE SUBSCRIBE OUR PAKTECHPOINT YOUTUBE CHANNEL

INSTALLATION OF RECIPROCATING COMPRESSOR

Please do the initial preparation for work.

Secure work permit and other applicable approved documents prior to work commence.

Tools and equipment shall be made operational and available for use. Ensure tools are color-coded accordingly.

Conduct lifting study & get approved lifting plan accordance with required cases.

Prior to the arrival of equipment on site, Contractor shall review the manufacturer’s requirement and the requirements of this specification regarding on site storage of the equipment. These requirements shall be incorporated to site preservation plan and adhere to in all respects.

Install barricades to confine the area for authorized personnel only.

Foundation for Installation of Reciprocating Compressor 

Confirm acceptances & turnover of civil works foundation/pedestals with a signed copy of works release notice.

After receiving foundation release note, the following points shall be checked.

 Distinct position (center) marking and height (level) marking on the foundation, It will be referred for alignment work of level and position.
 Size and Position of Anchor Hole

Using theodolite establish centerline of the equipment unit. Mark centerline on concrete foundation using paint/ prick punch.

Trace centerlines of foundation bolt holes with reference to gridlines. Check plumbness of anchor bolt.

Clean the surface thoroughly by blowing with oil-free from air compressor.

Center lines lost due to chipping operations will retrace anew.

The elevation of the chipped top foundations shall allow for at least 25 mm of grout under the base plate as per SAES-Q-005 (ARAMCO STANDARD) Concrete Foundation.