This article is about Material Receiving Checklist for UTP/STP Copper Cable of Building Telecom Distribution System as per International Codes and standards.
UTP/STP Copper Cable – Material Receiving Checklist
- Verify that the received materials have been inspected for damages and for compliance to applicable requirements.
- Verify that cable storage and protection is as per manufacturer’s recommendation.
- Verify that received cables comply with approved project PO specification and shall conform to all applicable requirements, standards, and specifications prior to release to be used as part of the work
- Verify that the received materials are new and unused.
- Verify that material and accessories are in accordance with the Saudi Aramco-approved project-specific design drawings, diagrams, schedules, lists, databases, and associated design documents
- For outdoors storage, verify that cable reels is supported off the ground and provided with a weatherproof (i.e., rain and dust-tight) cover per the manufacturer recommendations.
- General – Cable reels shall be stored away from open flame, fire, arc welding, brazing, grinding and other sources of high heat or ignition.
- Verify that received cables with cable jacket material not rated for exposure to sunlight shall be stored under a sunshade or indoors.
- Verify that materials identification procedure is implemented for the received items.
- Ensure that cable and accessories shall be traceable from the manufacturer and supplier through delivery, storage, fabrication, erection, installation, repair, modification and use.
- Verify that received UTP cables to be used for horizontal cabling within Saudi Aramco are Category 6 UTP cables.
- Verify and ensure that all cabling are identified and marked in accordance with Table 800-50 of the NEC.
Standards Codes and References for Telecom UTP/STP Copper Cable
1. SAES-T-916, Telecommunications Building Cable Systems.
2. Commercial Building Standard for Telecommunications Pathways and Spaces.
Backbone UTP/STP Copper Cable Installation | Inspection | Design
Telecom Cable Management Trays – Material Receiving Checklist
Telecom Equipment Racks & Accessories Material Receiving Checklist
Horizontal Connecting Hardware Material Receiving Checklist | Telecommunication
Horizontal UTP/STP Copper Cable Installation and Inspection
Telecom Closet / Telecom Equipment Room Size And Location.
Telecommunications Infrastructure Design Process.
ANSI/TIA/EIA 568-B Commercial Building Telecommunications Cabling Standard.
Telecommunications Outside Plant Systems Design SAES-T-938 Download.